United States › Grid › Interconnection queues › Virginia

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Virginia — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown86886.8 GW
Active in queue30.3 GW287 requests
Agreement signed7,318 MW72 requests
Withdrawn86886.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

868 requests · page 10 of 18
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Y1-008, Accomack County
Onshore wind
50.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2012target 2014
Battery storage project AF2-266, Charlotte County
Battery storage
50.0 MWWithdrawn / abandoned Charlotte, VAPJM Mar 2020target 2022
Battery storage project AH1-457, Spotsylvania County
Battery storage
50.0 MWWithdrawn / abandoned Spotsylvania, VAPJM Sep 2021target 2024
Solar project AH1-001, Frederick County
Solar
50.0 MWWithdrawn / abandoned Frederick, VAPJM Apr 2021target 2023
Battery storage project AH1-238, Caroline County
Battery storage
50.0 MWWithdrawn / abandoned Caroline, VAPJM Sep 2021target 2024
Solar project AF2-362, Lancaster County
Solar
50.0 MWWithdrawn / abandoned Lancaster, VAPJM Mar 2020target 2023
Solar + storage project AG1-547, Pittsylvania County
Solar + storage · Curie Solar, LLC
50.0 MWWithdrawn / abandoned Pittsylvania, VAPJM Sep 2020target 2024
Battery storage project AH2-143, City Of Suffolk County
Battery storage
50.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Feb 2022target 2024
Battery storage project AF1-066, Loudoun County
Battery storage
50.0 MWWithdrawn / abandoned Loudoun, VAPJM Aug 2019target 2021
Solar project AD2-201A, Pulaski County
Solar
50.0 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2018target 2021
Battery storage project AH1-450, Mecklenburg County
Battery storage
50.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Sep 2021target 2025
Solar project AH1-279, Isle Of Wight County
Solar
50.0 MWWithdrawn / abandoned Isle Of Wight, VAPJM Sep 2021target 2023
Solar project AB2-069, Mecklenburg County
Solar
49.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Mar 2016target 2018
Battery storage project AG1-185, Charlotte County
Battery storage · Drakes Branch Solar, LLC
48.9 MWWithdrawn / abandoned Charlotte, VAPJM Sep 2020target 2023
Solar project AG2-349, Frederick County
Solar
47.8 MWWithdrawn / abandoned Frederick, VAPJM Feb 2021target 2024
Other project U2-057, City Of Hopewell County
Other
47.6 MWWithdrawn / abandoned City Of Hopewell, VAPJM Jun 2008target 2010
Solar project AG1-428, Brunswick County
Solar · ACE Development Company II, LLC
46.8 MWWithdrawn / abandoned Brunswick, VAPJM Sep 2020target 2024
Solar + storage project LGE-GIS-2022-008, Lee County
Solar + storage
45.0 MWWithdrawn / abandoned Lee, VASoutheast Sep 2022target 2024
Solar + storage project AD1-050, Mecklenburg County
Solar + storage
45.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Aug 2017target 2019
Solar project AG2-368, Buckingham County
Solar
45.0 MWWithdrawn / abandoned Buckingham, VAPJM Mar 2021target 2025
Solar + storage project AH2-208, Lee County
Solar + storage
45.0 MWWithdrawn / abandoned Lee, VAPJM Mar 2022target 2024
Solar project AG2-432, Wythe County
Solar
45.0 MWWithdrawn / abandoned Wythe, VAPJM Mar 2021target 2023
Central Solar Park
Onshore wind
45.0 MWWithdrawn / abandoned Roanoke, VAPJM Feb 2010target 2012
Solar + storage project AF2-055, Northampton County
Solar + storage
45.0 MWWithdrawn / abandoned Northampton, VAPJM Jan 2020target 2025
Solar project AE2-026, Louisa County
Solar
44.8 MWWithdrawn / abandoned Louisa, VAPJM Dec 2018target 2020
Solar project AF1-079, Louisa County
Solar
44.8 MWWithdrawn / abandoned Louisa, VAPJM Aug 2019target 2021
Solar + storage project AH1-214, Campbell County
Solar + storage
44.1 MWWithdrawn / abandoned Campbell, VAPJM Sep 2021target 2025
Solar project AE2-231, Caroline County
Solar
44.0 MWWithdrawn / abandoned Caroline, VAPJM Mar 2019target 2022
Battery storage project AH1-288, Charles City County
Battery storage
43.2 MWWithdrawn / abandoned Charles City, VAPJM Sep 2021target 2025
Solar project AG2-064, Caroline County
Solar
41.0 MWWithdrawn / abandoned Caroline, VAPJM Dec 2020target 2023
Onshore wind project J01, Highland County
Onshore wind
41.0 MWWithdrawn / abandoned Highland, VAPJM Aug 2002target 2004
Solar project LGE-GIS-2022-002, Wise County
Solar
40.0 MWWithdrawn / abandoned Wise, VASoutheast May 2022target 2025
Solar project AH1-168, Caroline County
Solar
40.0 MWWithdrawn / abandoned Caroline, VAPJM Aug 2021target 2026
Battery storage project AH1-080, City Of Virginia Beach County
Battery storage
40.0 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Jul 2021target 2025
Solar project AE1-164, Accomack County
Solar
40.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2018target 2021
Solar project AB2-147, Greensville County
Solar
40.0 MWWithdrawn / abandoned Greensville, VAPJM Apr 2016target 2017
Solar + storage project AG2-609, Orange County
Solar + storage
40.0 MWWithdrawn / abandoned Orange, VAPJM Mar 2021target 2023
Carvers Creek LLC
Battery storage · Carvers Creek LLC
40.0 MWWithdrawn / abandoned Gloucester, VAPJM Sep 2021target 2024
Solar project AI2-033, Sussex County
Solar
40.0 MWWithdrawn / abandoned Sussex, VAPJM Jan 2023target 2024
Battery storage project AG1-150, Accomack County
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2020target 2021
Battery storage project AG2-187, Amherst County
Battery storage
40.0 MWWithdrawn / abandoned Amherst, VAPJM Feb 2021target 2024
Scout Energy Storage
Battery storage
40.0 MWWithdrawn / abandoned Accomack, VAPJM Jan 2020target 2021
Battery storage project AG2-338, Sussex County
Battery storage · Cassius Blue Solar LLC
40.0 MWWithdrawn / abandoned Sussex, VAPJM Apr 2025target 2024
Battery storage project AH1-352, Campbell County
Battery storage · Altavista Solar, LLC
40.0 MWWithdrawn / abandoned Campbell, VAPJM Sep 2021target 2023
Battery storage project AE2-188, Culpeper County
Battery storage
40.0 MWWithdrawn / abandoned Culpeper, VAPJM Mar 2019target 2020
Bartonsville Energy Facility
Solar
40.0 MWWithdrawn / abandoned Frederick, VAPJM Sep 2020target 2023
Solar project AB2-150, Greensville County
Solar
40.0 MWWithdrawn / abandoned Greensville, VAPJM Apr 2016target 2017
Battery storage project AH1-640, Campbell County
Battery storage
40.0 MWWithdrawn / abandoned Campbell, VAPJM Sep 2021target 2025
Highland New Wind
Onshore wind
39.0 MWWithdrawn / abandoned Highland, VAPJM Sep 2004target 2021
Solar + storage project AI1-108, Rockingham County
Solar + storage
38.5 MWWithdrawn / abandoned Rockingham, VAPJM Aug 2022target 2026
Page 10 of 18

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)