BATTERY STORAGE Β· PJM

Battery storage project AH2-143, City Of Suffolk County

Battery storage project AH2-143, City Of Suffolk County is a 50.0 MW battery storage request withdrawn in the PJM interconnection queue, in City Of Suffolk County, Virginia, connecting to Dominion.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2022 (completed)
  2. Withdrawn / abandonedApr 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH2-143
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Location
City Of Suffolk County, Virginia
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 February 2022
Proposed online date
December 2024
Withdrawn
April 2022

Location

Marker shows the centre of City Of Suffolk County; the queue data does not give exact sites.

Power plants in Virginia Β· Transmission lines in Virginia

Other requests in City Of Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem