United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 10 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Chesterfield Unit #6
Coal
27.0 MWOperating Chesterfield, VAPJM Jul 20072010
River Energy Center
Gas
27.0 MWOperating Cook, ILPJM Mar 20082013
Bear Creek WF
Onshore wind
26.0 MWOperating Luzerne, PAPJM Jan 20042006
Harrisburg Municipal Solid Waste Authority
Other
26.0 MWOperating Dauphin, PAPJM Jan 20032006
Salem 1 & 2
Nuclear
26.0 MWOperating Salem, NJPJM Jan 20002001
NIH Unit 1
Other
25.0 MWOperating Montgomery, MDPJM Jul 20002004
Phillips Island
Gas
25.0 MWOperating Philadelphia, PAPJM Oct 20012004
Red Lion Energy Center
Other
24.9 MWOperating New Castle, DEPJM Apr 20112012
Nelson Energy Center
Gas
24.4 MWOperating Lee, ILPJM Sep 20182023
Hudson Generating Station
Coal
24.0 MWOperating Hudson, NJPJM Dec 20102012
Conowingo Hydro Station
Hydro
24.0 MWOperating Harford, MDPJM Jan 20072010
Kearny Generating Station
Gas
24.0 MWOperating Hudson, NJPJM Feb 20132015
Locust Ridge WF
Onshore wind
24.0 MWOperating Schuylkill, PAPJM Nov 20042006
Yankee 1-7
Gas
23.5 MWOperating Montgomery, OHPJM Mar 20192022
Orchard Park Generating Station
Other
23.3 MWOperating Franklin, PAPJM Jul 20022004
Linden Generating Station
Gas
23.0 MWOperating Union, NJPJM Sep 20132016
Eagle Point
Gas
22.9 MWOperating Gloucester, NJPJM Mar 20112012
City of Rochelle
Other
22.0 MWOperating Ogle, ILPJM Feb 20052005
Bellemeade
Gas
22.0 MWOperating City Of Richmond, VAPJM Jul 20072010
Stuart Electric Generating Station
Coal
20.5 MWOperating Brown, OHPJM Feb 20142015
Norge Solar
Solar
20.0 MWOperating James City, VAPJM Sep 20202023
Dry Bridge Energy Center
Battery storage
20.0 MWOperating Chesterfield, VAPJM Feb 20202023
Lyons Solar
Solar
20.0 MWOperating Berks, PAPJM Mar 20182023
Big Sandy #1
Gas
20.0 MWOperating Lawrence, KYPJM Jan 20072016
Clinch River Power Plant
Gas
20.0 MWOperating Russell, VAPJM Feb 20132016
Rockford II Energy Center
Gas
20.0 MWOperating Winnebago, ILPJM Oct 20162021
Warren County Power Station
Gas
20.0 MWOperating Warren, VAPJM Mar 20172018
Mechanicsville Solar
Solar
20.0 MWOperating Hanover, VAPJM Jul 20152020
Ladysmith Unit 4
Other
20.0 MWOperating Caroline, VAPJM Apr 20082009
MeadWestvaco Covington Mill Site
Other
20.0 MWOperating VAPJM Apr 20122013
Kelford Solar Park
Solar
20.0 MWOperating Bertie, NCPJM Mar 20142015
Winterberry Solar
Solar
20.0 MWOperating Gloucester, VAPJM Feb 20202024
West Chicago Energy Storage
Battery storage
20.0 MWOperating Dupage, ILPJM Oct 20132015
St. Thomas Township Solar Facility II
Solar
20.0 MWOperating Franklin, PAPJM Oct 20152020
Hilltop Energy Center Facility
Gas
20.0 MWOperating Greene, PAPJM Oct 20152021
Atlantic-RedBank 34.5kV Solar
Solar
20.0 MWOperating Monmouth, NJPJM Apr 20152019
SPSA Navy Power Plant
Other
20.0 MWOperating City Of Portsmouth, VAPJM Nov 20072008
Gavin 2
Coal
20.0 MWOperating Adams, OHPJM Jan 20062009
CL-Viaduct
Solar
20.0 MWOperating Clearfield, PAPJM Mar 20192023
Handsome Lake
Gas
20.0 MWOperating Venango, PAPJM May 20072007
University Park North Energy Center
Gas
20.0 MWOperating Will, ILPJM Oct 20142016
Geneva Energy LLC
Other
20.0 MWOperating Adams, ILPJM Mar 20052005
Elizabeth River GT3
Gas
20.0 MWOperating City Of Chesapeake, VAPJM Jul 20072008
City of Rochelle, IL
Other
20.0 MWOperating Ogle, ILPJM Jul 20042005
Montross Solar Facility
Solar
20.0 MWOperating Westmoreland, VAPJM Oct 20162018
Cottontail Solar 2
Solar
20.0 MWOperating York, PAPJM Mar 20182024
Solidago Solar
Solar
20.0 MWOperating Isle Of Wight, VAPJM Sep 20182023
Solar project AD1-061, Franklin County
Solar
20.0 MWOperating Franklin, PAPJM Aug 20172022
Halifax County Solar
Solar
20.0 MWOperating Halifax, VAPJM Aug 20172024
St. Thomas Township Solar Facility
Solar
20.0 MWOperating Franklin, PAPJM Oct 20152020
Page 10 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)