Montross Solar Facility

Montross Solar Facility is a 20.0 MW solar request built and operating in the PJM interconnection queue, in Westmoreland County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Oct 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AC1-118
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Westmoreland 34.5kV
Location
Westmoreland County, Virginia
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
27 October 2016
Proposed online date
February 2019
Came online
December 2018

Location

Marker shows the centre of Westmoreland County; the queue data does not give exact sites.