United States βΊ Grid βΊ Interconnection queues βΊ Illinois
GAS Β· PJMNelson Energy Center
Nelson Energy Center is a 24.4 MW gas request built and operating in the PJM interconnection queue, in Lee County, Illinois, connecting to ComEd.
Request details
- Queue ID
- AE1-134
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Nelson 345 kV
- Location
- Lee County, Illinois
- Technology
- Gas: 24.4 MW
- Total requested
- 24.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 24 September 2018
- Proposed online date
- June 2023
- Came online
- May 2023
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Shady Oaks Wind Power ProjectOnshore wind Β· 106 MW Β· agreement signed
- Steward Creek SolarSolar Β· 300 MW Β· in study
- South Dixon SolarSolar Β· 300 MW Β· in study
- Solar project AH1-151, Lee CountySolar Β· 200 MW Β· in study
- Solar project AH1-150, Lee CountySolar Β· 200 MW Β· in study
- Steward Creek SolarSolar Β· 200 MW Β· in study
- South Dixon SolarSolar Β· 200 MW Β· in study
- Solar project AH1-044, Lee CountySolar Β· 200 MW Β· in study
- Solar project AH1-338, Lee CountySolar Β· 180 MW Β· in study
- Battery storage project AH2-015, Lee CountyBattery storage Β· 110 MW Β· in study
- Steward Creek SolarSolar Β· 100 MW Β· in study
- Battery storage project AH2-123, Lee CountyBattery storage Β· 100 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem