Stripe is a 4.98 MW solar farm in Yorkshire and the Humber, England, operated by Anesco. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Yorkshire and the Humber
- England
Key facts
- Installed capacity
- 4.98 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Anesco
- Region
- Yorkshire and the Humber
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- DL10 7PW
- Coordinates
- 54.4175, -1.6989
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Stripe compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.98 MW station would generate roughly 4.4 GWh of electricity in a year, similar to the annual use of about 1,620 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Yorkshire and the Humber All run by AnescoNearby generating sites
- East Appleton Β· 4.98 MW solar farm7.8 km
- Hunger Hill Β· 5 MW solar farm17.0 km
- Ainderby Β· 4.96 MW solar farm17.2 km
- Moor House Wind Farm Β· 12 MW onshore wind farm21.8 km
- School Aycliffe Β· 5 MW solar farm22.2 km
- High Meadow Β· 3.89 MW solar farm27.6 km
- Sandhutton Β· 5 MW solar farm28.0 km
- Lambs Hill Wind Farm Β· 8 MW onshore wind farm28.0 km
Also operated by Anesco
Anesco operates 136 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Land at Stripe Farm
- Developer / operator
- Gresham House
- Planning authority
- North Yorkshire
- Planning reference
- 15/00449/FULL
- Application submitted
- 16 June 2015
- Permission granted
- 14 September 2015
- Construction started
- 15 January 2016
- Began operating
- 28 March 2016
- Capacity in planning record
- 5 MW
- Address
- Land West Of East Appleton Hal, East Appleton, Richmond, North Yorkshire, North Yorkshire, DL10 7QE
- REPD reference
- 5403
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.