Ainderby
Ainderby is a 4.96 MW solar farm in Yorkshire and the Humber, England, operated by Greencoat Capital. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Yorkshire and the Humber
- England
Key facts
- Installed capacity
- 4.96 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Greencoat Capital
- Region
- Yorkshire and the Humber
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- DL7 9PZ
- Coordinates
- 54.3236, -1.4877
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Ainderby compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 4.96 MW station would generate roughly 4.3 GWh of electricity in a year, similar to the annual use of about 1,610 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Yorkshire and the Humber All run by Greencoat CapitalNearby generating sites
- East Appleton Β· 4.98 MW solar farm10.4 km
- Sandhutton Β· 5 MW solar farm11.2 km
- Stripe Β· 4.98 MW solar farm17.2 km
- Hunger Hill Β· 5 MW solar farm20.4 km
- Cold Harbour Β· 5 MW solar farm20.4 km
- Seamer Β· 10.3 MW onshore wind farm24.1 km
- Peter Hill Β· 5 MW solar farm25.2 km
- Lambs Hill Wind Farm Β· 8 MW onshore wind farm26.9 km
Also operated by Greencoat Capital
Greencoat Capital operates 195 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- North East of Ainderby Steeple
- Developer / operator
- Renesola UK
- Planning authority
- North Yorkshire
- Planning reference
- 14/00471/FUL
- Application submitted
- 5 March 2014
- Permission granted
- 24 December 2014
- Construction started
- 24 January 2017
- Began operating
- 24 March 2017
- Capacity in planning record
- 5.9 MW
- Address
- Land North East Of Ainderby Steeple North Yorkshire, North Yorkshire
- REPD reference
- 1927
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.