Seamer
Seamer is a 10.3 MW onshore wind farm in North East England, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- Onshore
- North East
- England
Key facts
- Installed capacity
- 10.3 MW
- Status
- Operational
- Technology
- Wind Β· Onshore
- Operator
- Venitent Energy Services
- Region
- North East
- Country
- England
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- TS15 9JH
- Coordinates
- 54.4942, -1.2585
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How Seamer compares
At a typical UK load factor for this technology (about 26% of the maximum possible output), a 10.3 MW station would generate roughly 23 GWh of electricity in a year, similar to the annual use of about 8,650 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.
All UK wind farms Wind farms in North East All run by Venitent Energy ServicesNearby generating sites
- Lambs Hill Wind Farm Β· 8 MW onshore wind farm7.3 km
- Wilton International Β· 120 MW gas-fired power station11.8 km
- Wilton 10 Biomass Β· 33.3 MW biomass power station12.4 km
- Woodhouse PV Β· 4.88 MW solar farm12.6 km
- Guisborough Β· 5 MW solar farm13.2 km
- Wilton 11 Β· 49 MW energy-from-waste plant13.6 km
- High Meadow Β· 3.89 MW solar farm13.6 km
- Viking Β· 50 MW open-cycle gas power station13.9 km
Also operated by Venitent Energy Services
Venitent Energy Services operates 33 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Seamer Wind Farm - Hambleton
- Developer / operator
- Infinis, previously Broadview Energy
- Planning authority
- Stockton-on-Tees
- Planning reference
- 09/00859/FUL
- Application submitted
- 27 March 2009
- Permission granted
- 18 September 2009
- Construction started
- 1 October 2011
- Began operating
- 1 November 2012
- Capacity in planning record
- 4 MW
- Address
- Land Adjacent Hilton Road, Seamer, Middlesbrough, Cleveland
- REPD reference
- 3791
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.