WIND Β· OPERATIONAL

Galawhistle

Galawhistle is a 66 MW onshore wind farm in Scotland, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland

Key facts

Installed capacity
66 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Venitent Energy Services
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Postcode
ML11 0SJ
Coordinates
55.5395, -3.9754

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Galawhistle compares

80th of 488largest wind farms in the UK register
40th of 199in Scotland
0.22%of listed UK wind farms capacity
β‰ˆ 150 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 66 MW station would generate roughly 150 GWh of electricity in a year, similar to the annual use of about 55,670 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Venitent Energy Services

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Developer / operator
Ventient (formerly Infinis)
Planning authority
Scottish Government (S36)
Application submitted
12 March 2010
Permission granted
8 August 2012
Construction started
18 June 2015
Began operating
15 February 2017
Capacity in planning record
66 MW
Address
7km east of Muirkirk in East Ayrshire and 4km west of Douglas in South Lanarkshire, Strathclyde
REPD reference
4368

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.