WIND Β· OPERATIONAL

Farr

Farr is a 92 MW onshore wind farm in Scotland, operated by Venitent Energy Services. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • Onshore
  • Scotland

Key facts

Installed capacity
92 MW
Status
Operational
Technology
Wind Β· Onshore
Operator
Venitent Energy Services
Region
Scotland
Country
Scotland
Grid connection (DUKES)
HV
Combined heat & power
No
Postcode
IV13 7ZA
Coordinates
57.3339, -4.1030

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Farr compares

60th of 488largest wind farms in the UK register
27th of 199in Scotland
0.31%of listed UK wind farms capacity
β‰ˆ 210 GWhillustrative output a year

At a typical UK load factor for this technology (about 26% of the maximum possible output), a 92 MW station would generate roughly 210 GWh of electricity in a year, similar to the annual use of about 77,610 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Wind farms turn the kinetic energy of the wind into electricity with turbines. Output varies with wind speed. Offshore sites usually see stronger, steadier winds than onshore sites and so generate more per MW of capacity.

All UK wind farms Wind farms in Scotland All run by Venitent Energy Services

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Farr Wind Farm
Developer / operator
Innogy (formerly RWE npower)
Planning authority
Scottish Government (S36)
Application submitted
12 September 2002
Permission granted
5 October 2004
Construction started
1 April 2005
Began operating
1 October 2005
Capacity in planning record
92 MW
Address
Tomatin Inverness, Highland
REPD reference
4676

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026