NI Cluster Belfast Road
NI Cluster Belfast Road is a 9.99 MW solar farm in Northern Ireland, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).
- PV
- Northern Ireland
Key facts
- Installed capacity
- 9.99 MW
- Status
- Operational
- Technology
- Solar Β· PV
- Operator
- Lightsource BP
- Region
- Northern Ireland
- Country
- Northern Ireland
- Grid connection (DUKES)
- LV
- Combined heat & power
- No
- Postcode
- BT29 4TH
- Coordinates
- 54.6356, -6.1148
Location
Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.
How NI Cluster Belfast Road compares
At a typical UK load factor for this technology (about 10% of the maximum possible output), a 9.99 MW station would generate roughly 8.8 GWh of electricity in a year, similar to the annual use of about 3,240 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.
Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.
All UK solar farms Solar farms in Northern Ireland All run by Lightsource BPNearby generating sites
- NI Cluster Knockairn Road Β· 5.4 MW solar farm4.5 km
- NI Cluster Moira Road Β· 5.94 MW solar farm5.7 km
- Crookedstone Β· 4.83 MW solar farm6.7 km
- Brett Martin Β· 6.49 MW solar farm7.7 km
- NI Cluster Hillside Β· 5.4 MW solar farm9.4 km
- NI Cluster Lough Road Β· 5.4 MW solar farm9.9 km
- Elliot's Hill Β· 5 MW onshore wind farm11.5 km
- Lisburn Β· 20.5 MW solar farm13.1 km
Also operated by Lightsource BP
Lightsource BP operates 129 sites in the register. Largest first:
Planning history
From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.
- Planning status
- Operational
- Site name in planning record
- Lands West of Belfast Road
- Developer / operator
- Lightsource Renewable Energy
- Planning authority
- Antrim and Newtownabbey
- Planning reference
- LA03/2015/0257/F
- Application submitted
- 29 June 2015
- Permission granted
- 23 December 2015
- Construction started
- 15 February 2017
- Began operating
- 15 March 2017
- Capacity in planning record
- 10 MW
- Address
- Lands Approximately 140m West, 66 Belfast Road, Nutts Corner, Crumlin, Co Antrim, Co. Antrim, BT29 4TH
- REPD reference
- 5435
Source
Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β operational at end of May 2025.
Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026
Spotted an error? Tell us and we will check it against the source.