Brett Martin is a 6.49 MW solar farm in Northern Ireland, operated by Lightsource BP. The UK government lists it as operational in its register of power stations (DUKES table 5.11, May 2025).

  • PV
  • Northern Ireland
Project stageOperating
  1. PlanningDec 2015 (completed)
  2. ConsentedJul 2016 (completed)
  3. ConstructionDec 2017 (completed)
  4. OperatingFeb 2018 (current stage)
  5. Closed (not yet reached)

Planning dates from the Renewable Energy Planning Database; operating status from DUKES table 5.11.

Key facts

Installed capacity
6.49 MW
Status
Operational
Technology
Solar Β· PV
Operator
Lightsource BP
Region
Northern Ireland
Country
Northern Ireland
Grid connection (DUKES)
LV
Combined heat & power
No
Postcode
BT36 4QU
Coordinates
54.6754, -6.0160

Location

Map position from the published coordinates. For small sites this can be an approximate point rather than the exact boundary. Map Β© OpenStreetMap contributors.

How Brett Martin compares

205th of 662largest solar farms in the UK register
7th of 16in Northern Ireland
0.11%of listed UK solar farms capacity
β‰ˆ 5.7 GWhillustrative output a year

At a typical UK load factor for this technology (about 10% of the maximum possible output), a 6.49 MW station would generate roughly 5.7 GWh of electricity in a year, similar to the annual use of about 2,110 homes at 2,700 kWh each. This is an illustrative estimate, not the station's metered output: real generation varies with weather, availability and grid constraints.

Solar photovoltaic (PV) sites generate electricity from sunlight. Panels produce direct current, which inverters convert to alternating current for the grid. Output follows daylight and the seasons, so annual generation is a small fraction of the maximum possible.

All UK solar farms Solar farms in Northern Ireland All run by Lightsource BP

Planning history

From the government's Renewable Energy Planning Database (REPD), matched to this site by location, capacity and name.

Planning status
Operational
Site name in planning record
Gibson Farm
Developer / operator
Lightsource Renewable Energy
Planning authority
Antrim and Newtownabbey
Planning reference
LA03/2015/0655/F
Application submitted
4 December 2015
Permission granted
26 July 2016
Construction started
11 December 2017
Began operating
28 February 2018
Capacity in planning record
6.4 MW
Address
Land at Gibson Farm, Sealstown Road, Newtownabbey, Co. Antrim, BT36 4QU
REPD reference
5977

Source

Department for Energy Security and Net Zero (DESNZ), Digest of UK Energy Statistics (DUKES), table 5.11: power stations in the United Kingdom β€” operational at end of May 2025. Capacity is installed capacity as published, not current output. Status reflects the source date, not live operation.
View the original source
Last checked by Octary: 15 July 2026

Spotted an error? Tell us and we will check it against the source.