Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Battery storage projects in the connection queue

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown609178.0 GW in total
In planning609scoping or awaiting consent
Consented or building126closest to connecting
Built79connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

609 projects · page 4 of 13
ProjectCapacityStageConnection siteFrom
Tyler Hill Bicker Fen
Battery storage · FRV Powertek Limited
400 MWScoping Coddington 400kV Substation
National Grid (England & Wales)
May 2035
Woodbridge - Noventum
Battery storage · Noventum Power Solar 16 Limited
400 MWScoping South Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
Noventum- Bridgwater
Battery storage · Noventum Power Solar 13 Limited
380 MWScoping Woolavington 400kV Substation
National Grid (England & Wales)
Oct 2037
Denny BESS
Battery storage · Igp Energy Storage 3 Limited
350 MWScoping Denny North
SP Transmission (south Scotland)
Oct 2030
Westfield BESS
Battery storage · Brockwell Energy Limited
350 MWScoping Westfield 400kV Substation
SP Transmission (south Scotland)
Oct 2031
Whitson BESS NP
Battery storage · Equinor New Energy Limited
350 MWScoping South Wales East Node A 275kV Substation
National Grid (England & Wales)
Oct 2037
Shotwick BESS
Battery storage · Shotwick Land Limited
350 MWScoping Merseyside Connection Node A 400Kv Substation
National Grid (England & Wales)
Oct 2037
Cilfynydd BESS
Battery storage · Cilfynydd BESS Limited
350 MWScoping Cilfynydd 400kV Substation
National Grid (England & Wales)
Oct 2037
SAE Usk 1
Battery storage · Afon Wysg Energy Limited
349 MWScoping South Wales East Node A 275kV Substation
National Grid (England & Wales)
Oct 2037
ESB Harker BESS
Battery storage · Esb (Harker) Ltd
342 MWScoping Harker 400kV Substation
National Grid (England & Wales)
Oct 2039
Pittlesheugh Farm
Battery storage · Pittlesheugh Farm BESS Limited
340 MWScoping Eccles 400/132kV
SP Transmission (south Scotland)
Oct 2030
High Mathernock Battery Storage
Battery storage · Harmony HM Limited
334 MWScoping High Mathernock 132Kv Substation
SP Transmission (south Scotland)
Oct 2029
Zenobe Butler's Wood BESS
Battery storage · Zenobe Energy Limited
330 MWScoping Butlers Wood 400kV Substation
National Grid (England & Wales)
Oct 2034
Hurst BESS
Battery storage · Luminous Energy Group Limited
320 MWScoping North Kent Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2037
AGS Calderside Battery Energy Storage System
Battery storage · Advance Grid Solutions Limited
300 MWScoping Ags Calderside 275Kv Substation
SP Transmission (south Scotland)
Oct 2029
Aitkenhead Farm BESS
Battery storage · Aitkenhead Storage Facility Limited
300 MWScoping Clydesmill 275/33kV
SP Transmission (south Scotland)
Apr 2033
Alcemi Midmill BESS
Battery storage · Alcemi Storage Developments 2 Limited
300 MWScoping Kintore 275kV
SSEN Transmission (north Scotland)
Dec 2029
Boom Power Seaton Hill Generation HUB
Battery storage · Seatonhill Storage Facility Limited
300 MWScoping Cockenzie 400/275kV
SP Transmission (south Scotland)
Oct 2033
Coddington BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Trent Valley South Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Coylton Farm
Battery storage · New Energy Partnership Limited
300 MWAwaiting Consents Coylton 275/33kV Substation
SP Transmission (south Scotland)
Oct 2037
Craig Moss Farm
Battery storage · Qair Renewables UK Limited
300 MWScoping Craig Moss Farm 132kV Substation
SP Transmission (south Scotland)
Oct 2036
Crossgatehall BESS
Battery storage · De 001 Limited
300 MWScoping Smeaton 400/275kV
SP Transmission (south Scotland)
Oct 2033
Didcot Energy Park
Battery storage · Brockwell Storage & Solar Limited
300 MWAwaiting Consents Didcot 400kV Substation
National Grid (England & Wales)
Oct 2027
Dragon Green BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Elmya Bathgate BESS
Battery storage · Rpc Elmya Carnation Bathgate Limited
300 MWScoping Armadale 400kv Substation
SP Transmission (south Scotland)
Oct 2031
Elmya Melbourne BESS
Battery storage · Elmya Rpc UK Melbourne Limited
300 MWScoping Thornton 400kV Substation
National Grid (England & Wales)
Oct 2039
Elmya Rednal
Battery storage · Elmya Rpc UK Rednal Limited
300 MWAwaiting Consents Ironbridge 400kV Substation
National Grid (England & Wales)
Oct 2034
Gf Sellindge BESS
Battery storage · GF Sellindge Energy Ltd
300 MWScoping East Kent connection node A 400kV Substation
National Grid (England & Wales)
Oct 2036
Great Coates BESS
Battery storage · Bruton One BESS Limited
300 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Oct 2035
Gresham House Dalmarnock BESS
Battery storage · Energyhubdevelopments Limited
300 MWScoping Gresham House Dalmarnock Bess 132kv Substation
SP Transmission (south Scotland)
Apr 2030
Gresham House Kincardine BESS
Battery storage · Flavusia Ltd
300 MWScoping Gresham House Kincardine BESS 275/132kV substation
SP Transmission (south Scotland)
Oct 2029
Kynachan
Battery storage · Geocore Ltd
300 MWScoping Kynachan BESS 132kV Substation
SSEN Transmission (north Scotland)
Oct 2035
Lightsource Bodelwyddan
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping Cheshire Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Lightsource Pyworthy
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping West Country Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Lightsource Rhigos BESS
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Littlebrook BESS
Battery storage · Ecodev (South) Ltd
300 MWScoping Littlebrook 132kV Substation
National Grid (England & Wales)
Oct 2027
Newarthill Energy Park
Battery storage · Dalzell (Newarthill) Ltd
300 MWScoping Newarthill Energy Park 275kV Substation
SP Transmission (south Scotland)
Oct 2029
NorthFleet 2 BESS
Battery storage · Cse41 Limited
300 MWScoping NorthFleet 400kV Substation
National Grid (England & Wales)
Oct 2028
Overton Grange BESS
Battery storage · Anesco Limited
300 MWScoping Wearside Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Red Moss Farm
Battery storage · Qair Renewables UK Limited
300 MWScoping Red Moss Farm 132kV Substation
SP Transmission (south Scotland)
May 2031
Redhall BESS
Battery storage · Anesco Limited
300 MWScoping Wearside Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Spittal BESS
Battery storage · Field Spittal Ltd
300 MWScoping Spittal 132kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Stirling BESS
Battery storage · Anesco Limited
300 MWScoping Peterhead 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Strathaven BESS
Battery storage · Igp Energy Storage 2 Limited
300 MWScoping Strathaven 400kV Substation
SP Transmission (south Scotland)
Oct 2033
Thorney Edge
Battery storage · ARL Energy Development Limited
300 MWScoping Cellarhead 400kV Substation
National Grid (England & Wales)
Nov 2037
Waltham Cross BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping London North East Connection Node A 400kV
National Grid (England & Wales)
Oct 2033
Zenobe Hartmoor BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Wearside Connection Node A 275kV Substation
National Grid (England & Wales)
Oct 2035
Zenobe Hawthorn Pit BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Wearside Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
Zenobe Little Horsted BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Zenobe Necton BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Necton 400kV Substation
National Grid (England & Wales)
Oct 2034
Page 4 of 13

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.