Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown1,329586.0 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

1,329 projects · page 3 of 27
ProjectCapacityStageConnection siteFrom
Saltend
Gas · Saltend Cogeneration Company Limited
1.1 GWBuilt Saltend South 400kV Substation
National Grid (England & Wales)
Five Estuaries Offshore Wind Farm
Offshore wind · Five Estuaries Offshore Wind Farm Limited
1.1 GWScoping Five Estuaries 220/66 kV Offshore Substation
National Grid (England & Wales)
Oct 2030
Bradwell Energy Park
Solar + storage · Low Carbon Solar Park 28 Limited
1.1 GWScoping Rayleigh 400kV Substation
National Grid (England & Wales)
Oct 2034
ElecLink
Interconnector · Eleclink Limited
1.1 GWBuilt Sellindge 400kV Substation
National Grid (England & Wales)
Project Cobalt
Interconnector · Getlink Projects 2 Limited
1.1 GWScoping East Kent Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2036
Nemo Link
Interconnector · Nemo Link Limited
1.0 GWBuilt Richborough 400kV Substation
National Grid (England & Wales)
Butlers Wood Green Energy Centre
Solar + storage · Butlers Wood Ng Limited
1.0 GWAwaiting Consents Butlers Wood 400kV Substation
National Grid (England & Wales)
Oct 2031
Cilfynydd Green Energy Centre
Solar + storage · Cilfynydd Ng Limited
1.0 GWAwaiting Consents Cilfynydd 400kV Substation
National Grid (England & Wales)
Oct 2033
Drakelow Green Energy Centre
Solar + storage · Drakelow Ng Limited
1.0 GWAwaiting Consents Drakelow 400kV Substation
National Grid (England & Wales)
Oct 2029
East Claydon Green Energy Centre
Solar + storage · East Claydon Green Ng Limited
1.0 GWAwaiting Consents East Claydon 400kV Substation
National Grid (England & Wales)
Oct 2034
Enderby Green Energy Centre
Solar + storage · Enderby BESS Limited
1.0 GWAwaiting Consents Enderby 400kV Substation
National Grid (England & Wales)
Oct 2028
Feckenham Green Energy Centre
Solar + storage · Feckenham Green Ng Limited
1.0 GWScoping Feckenham 400kV Substation
National Grid (England & Wales)
Oct 2032
Hams Hall Green Energy Centre
Solar + storage · Hams Hall Ng Limited
1.0 GWScoping Hams Hall 400kV Substation
National Grid (England & Wales)
Oct 2032
Hawthorn Pit Green Energy Centre
Solar + storage · Hawthorn Pit Ng Limited
1.0 GWAwaiting Consents Hawthorn Pit 400kV Substation
National Grid (England & Wales)
Oct 2032
Mablethorpe Green Energy Centre
Solar + storage · Mablethorpe Ng Limited
1.0 GWAwaiting Consents Mablethorpe 400kV Substation
National Grid (England & Wales)
Oct 2033
Overton Green Energy Centre
Solar + storage · Overton Ng Limited
1.0 GWAwaiting Consents Overton 275kV
National Grid (England & Wales)
Oct 2035
Pentir Green Energy Centre
Solar + storage · Innova Renewables Limited
1.0 GWAwaiting Consents Pentir 400kV Substation
National Grid (England & Wales)
Oct 2037
Swansea North Green Energy Centre
Solar + storage · Swansea North Green Ng Limited
1.0 GWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Oct 2033
Thorpe Marsh Green Energy Centre
Solar + storage · Thorpe Marsh Ng Ltd
1.0 GWAwaiting Consents Thorpe Marsh 400kV Substation
National Grid (England & Wales)
Aug 2032
Willington Green Energy Centre
Solar + storage · Willington Ng Limited
1.0 GWAwaiting Consents Willington 400kV Substation
National Grid (England & Wales)
Oct 2031
Cormoran Offshore Wind Farm
Offshore wind · South West Wind Holdco Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Mererid Offshore Wind Farm
Offshore wind · South West Wind Holdco Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Ossian 4 Offshore Wind Farm
Offshore wind · Ossian Offshore Wind Farm Limited
1.0 GWScoping Cousland 400kV
National Grid (England & Wales)
Oct 2033
Alcemi Bramford Battery Energy Storage Facility Phase 2
Battery storage · Alcemi Storage Developments 1 Limited
1.0 GWScoping South Anglia Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2034
Alverdiscott Farm
Solar + storage · Alverdiscott 10 Renewables Ltd
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Apr 2037
Amersham Main
Solar + storage · Amersham 10 Renewables Limited
1.0 GWScoping London North West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
BF88 Oakley
Solar + storage · Bluefield Renewable Developments Limited
1.0 GWScoping Chiltern Connection Node C 400kV Substation
National Grid (England & Wales)
Nov 2038
Biggleswade
Solar + storage · Biggleswade 10 Renewables Limited
1.0 GWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Biggleswade High Impact Green Energy Hub
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Oct 2034
Braintree
Solar + storage · Braintree 10 Renewables Limited
1.0 GWScoping Braintree 400kV Substation
National Grid (England & Wales)
Oct 2034
Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Leeds North Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2035
Bushbury
Solar · Bushbury 10 Renewables Limited
1.0 GWScoping Staffordshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Canterbury North
Solar + storage · Canterbury North 10 Renewables Limited
1.0 GWScoping East Kent Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2030
Celtic 2 Offshore Wind Farm
Offshore wind · RWE Offshore Wind
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
Celtic Sea Offshore Wind Farm (ESB)
Offshore wind · Esb Asset Development UK Limited
1.0 GWScoping Celtic Sea 275/66Kv Offshore Substation
National Grid (England & Wales)
Oct 2031
Coryton
Solar · Coryton 10 Renewables Limited
1.0 GWScoping South Anglia Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Daventry High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Derbyshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Didcot High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Appleford 400kV
National Grid (England & Wales)
Oct 2037
East Claydon High Impact Green Energy Hub (HIGEH) 1
Solar + storage · East Claydon Storage Limited
1.0 GWScoping East Claydon 400kV Substation
National Grid (England & Wales)
Dec 2036
Eaton Socon High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWScoping Eaton Socon 400kV Substation
National Grid (England & Wales)
Oct 2033
Equinor Celtic Sea 1
Offshore wind · Equinor New Energy Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
Equinor Celtic Sea 2
Offshore wind · Equinor New Energy Limited
1.0 GWScoping Equinor 66Kv Offshore Substation
National Grid (England & Wales)
Dec 2036
ER BR Energy
Solar + storage · Er Project Development Co Limited
1.0 GWScoping Tween Bridge 400kV
National Grid (England & Wales)
Oct 2035
ER LIL Energy
Solar + storage · Er Project Development Co Limited
1.0 GWScoping Hope 400kV Substation
National Grid (England & Wales)
Oct 2036
Gateway Energy Centre Power Station
Battery storage · Gateway Energy Centre Limited
1.0 GWConsents Approved Coryton South 400kV Substation
National Grid (England & Wales)
Oct 2029
Grendon High Impact Green Energy Hub (HIGEH) 1
Solar + storage · Telis Energy UK Limited
1.0 GWAwaiting Consents Lavendon 400Kv Substation
National Grid (England & Wales)
Oct 2033
Gwynt Glas Offshore Wind Farm 2
Offshore wind · Gwynt Glas Offshore Wind Farm Limited
1.0 GWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Dec 2036
High Marnham 400
Solar + storage · Enso Green Holdings X Limited
1.0 GWScoping High Marnham 400kV Substation
National Grid (England & Wales)
Oct 2034
Huntingdon High Impact Energy Hub 1
Solar + storage · Telis Energy UK Limited
1.0 GWAwaiting Consents West Anglia Connection Node H 400kVSubstation
National Grid (England & Wales)
Oct 2034
Huntingdon High Impact Energy Hub 2
Solar + storage · Telis Energy UK Limited
1.0 GWScoping West Anglia Connection Node H 400kVSubstation
National Grid (England & Wales)
Oct 2034
Page 3 of 27

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.