Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

East Claydon Green Energy Centre

East Claydon Green Energy Centre is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at East Claydon 400kV Substation, with capacity due from October 2034. The connection agreement is held by East Claydon Green Ng Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2034 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002383
Customer
East Claydon Green Ng Limited
Technology
Demand, Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
1.0 GW
Change in this agreement
+1.0 GW
Capacity effective from
1 October 2034
Connection site
East Claydon 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near East Claydon · Grid map

Other projects at East Claydon 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem