πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

Grid infrastructure β€Ί Connection queue β€Ί Solar + storage

SOLAR + STORAGE Β· NGET

ER LIL Energy

ER LIL Energy is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Hope 400kV Substation, with capacity due from October 2036. The connection agreement is held by Er Project Development Co Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2036 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003718
Customer
Er Project Development Co Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
1.0 GW
Change in this agreement
+1.0 GW
Capacity effective from
31 October 2036
Connection site
Hope 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near Hope Β· Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem