🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Swansea North Green Energy Centre

Swansea North Green Energy Centre is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Swansea North 400kV Substation, with capacity due from October 2033. The connection agreement is held by Swansea North Green Ng Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001794-2
Customer
Swansea North Green Ng Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
1.0 GW
Change in this agreement
+625 MW
Capacity effective from
31 October 2033
Connection site
Swansea North 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Swansea North · Grid map

Other projects at Swansea North 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem