Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · NGET

Alverdiscott Farm

Alverdiscott Farm is a 1.0 GW solar + storage project in planning, connecting to the National Grid (England & Wales) network at Alverdiscott 400kV Substation, with capacity due from April 2037. The connection agreement is held by Alverdiscott 10 Renewables Ltd.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Apr 2037 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-002554
Customer
Alverdiscott 10 Renewables Ltd
Technology
Energy Storage System, PV Array (Photo Voltaic/solar)
Total capacity
1.0 GW
Change in this agreement
+1.0 GW
Capacity effective from
24 April 2037
Connection site
Alverdiscott 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Alverdiscott · Grid map

Other projects at Alverdiscott 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem