Grid infrastructure βΊ Connection queue βΊ Interconnector
INTERCONNECTOR Β· NGETElecLink
ElecLink is a 1.1 GW interconnector project built and connected, connecting to the National Grid (England & Wales) network at Sellindge 400kV Substation. The connection agreement is held by Eleclink Limited.
Connection details
- NESO project number
- PRO-000286
- Customer
- Eleclink Limited
- Technology
- Interconnector
- Export capacity
- 1.1 GW
- Import capacity
- 1.0 GW
- Already connected
- 1.1 GW
- Connection site
- Sellindge 400kV Substation
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Interconnector
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Other projects at Sellindge 400kV Substation
- IFA InterconnectorInterconnector Β· 2.0 GW Β· Built
- Partridge Farm BESSBattery storage Β· 500 MW Β· Scoping
- Sellindge (Tertiary)Battery storage Β· 76 MW Β· Awaiting Consents
- Sellindge (Tertiary)Battery storage Β· 50 MW Β· Awaiting Consents
- Sellindge Grid Stability ServicesOther Β· 0 MW Β· Consents Approved
Source: NESO interconnector register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem