NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown968461.1 GW in total
In planning968scoping or awaiting consent
Consented or building149closest to connecting
Built212connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

968 projects · page 10 of 20
ProjectCapacityStageConnection siteFrom
Tween Bridge Solar Park
Solar + storage · RWE Renewables UK Solar and Storage Limited
340 MWScoping Trent Valley North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2029
Park Farm Hybrid Solar and BESS
Solar + storage · Voltalia UK Ltd
332 MWScoping Derbyshire Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Zenobe Butler's Wood BESS
Battery storage · Zenobe Energy Limited
330 MWScoping Butlers Wood 400kV Substation
National Grid (England & Wales)
Oct 2034
Creyke Beck Solar Farm
Solar · RWE Renewables UK Solar and Storage Limited
320 MWScoping Creyke Beck GSP
National Grid (England & Wales)
May 2033
Hurst BESS
Battery storage · Luminous Energy Group Limited
320 MWScoping North Kent Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2037
Calderdale Wind Farm 312MW
Onshore wind · Calderdale Wind Farm Ltd
312 MWScoping Leeds North Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
Chickerell
Solar + storage · Enso Green Holdings X Limited
300 MWAwaiting Consents Chickerell 400kV Substation
National Grid (England & Wales)
Oct 2037
Coddington BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Trent Valley South Connection Node A 400kV
National Grid (England & Wales)
Oct 2034
Cranwell Solar & BESS Farm
Solar + storage · Trio Power Limited
300 MWScoping Trent Valley South Connection Node C 400kV Substation
National Grid (England & Wales)
Oct 2034
Didcot Energy Park
Battery storage · Brockwell Storage & Solar Limited
300 MWAwaiting Consents Didcot 400kV Substation
National Grid (England & Wales)
Oct 2027
Dragon Green BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping Sussex and Romney Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Elmya Grange Road
Solar + storage · Elmya Rpc UK Grange Road Limited
300 MWAwaiting Consents Elmya Grange 400kV
National Grid (England & Wales)
Oct 2031
Elmya Melbourne BESS
Battery storage · Elmya Rpc UK Melbourne Limited
300 MWScoping Thornton 400kV Substation
National Grid (England & Wales)
Oct 2039
Elmya Rednal
Battery storage · Elmya Rpc UK Rednal Limited
300 MWAwaiting Consents Ironbridge 400kV Substation
National Grid (England & Wales)
Oct 2034
Gf Sellindge BESS
Battery storage · GF Sellindge Energy Ltd
300 MWScoping East Kent connection node A 400kV Substation
National Grid (England & Wales)
Oct 2036
Great Coates BESS
Battery storage · Bruton One BESS Limited
300 MWScoping Grimsby West 400kV Substation
National Grid (England & Wales)
Oct 2035
Gwynt Glas Offshore Wind Farm
Offshore wind · Gwynt Glas Offshore Wind Farm Limited
300 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
Langage 400
Solar + storage · Enso Green Holdings X Limited
300 MWScoping Langage 400kV Substation
National Grid (England & Wales)
Oct 2037
Lightsource Bodelwyddan
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping Cheshire Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2037
Lightsource Pyworthy
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping West Country Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Lightsource Rhigos BESS
Battery storage · Lightsource Renewable UK Development Limited
300 MWScoping South Wales West Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Littlebrook BESS
Battery storage · Ecodev (South) Ltd
300 MWScoping Littlebrook 132kV Substation
National Grid (England & Wales)
Oct 2027
Llywelyn Floating Offshore Wind Farm
Offshore wind · Renantis UK Limited
300 MWScoping Pembroke 400kV Substation
National Grid (England & Wales)
Mar 2029
Merlin Offshore Wind Farm
Offshore wind · Offshore Wind Limited
300 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
Morwind 300
Offshore wind · Morwind Ltd
300 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Oct 2031
NorthFleet 2 BESS
Battery storage · Cse41 Limited
300 MWScoping NorthFleet 400kV Substation
National Grid (England & Wales)
Oct 2028
Overton Grange BESS
Battery storage · Anesco Limited
300 MWScoping Wearside Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Petroc Offshore Wind Farm
Offshore wind · Bluefloat Energy UK Holdings Limited
300 MWScoping Alverdiscott 400kV Substation
National Grid (England & Wales)
Mar 2029
Redhall BESS
Battery storage · Anesco Limited
300 MWScoping Wearside Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Stoke Bardolph 400
Solar + storage · Enso Green Holdings Limited
300 MWScoping Stoke Bardolph 400kV Substation
National Grid (England & Wales)
Oct 2031
Swainsthorpe
Solar + storage · Lightsource Renewable UK Development Limited
300 MWScoping North Anglia Connection Node A 400kV
National Grid (England & Wales)
Oct 2037
Thorney Edge
Battery storage · ARL Energy Development Limited
300 MWScoping Cellarhead 400kV Substation
National Grid (England & Wales)
Nov 2037
Valorous Offshore Wind Farm
Offshore wind · Blue Gem Wind Limited
300 MWScoping Pembroke 400kV Substation
National Grid (England & Wales)
Oct 2031
Waltham Cross BESS
Battery storage · Shaw-Energi Ltd
300 MWScoping London North East Connection Node A 400kV
National Grid (England & Wales)
Oct 2033
Whiteleigh Farm
Solar + storage · Qair Renewables UK Limited
300 MWScoping Pyworthy 400kV Substation
National Grid (England & Wales)
Dec 2036
Zenobe Hartmoor BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Wearside Connection Node A 275kV Substation
National Grid (England & Wales)
Oct 2035
Zenobe Hawthorn Pit BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Wearside Connection Node B 400kV Substation
National Grid (England & Wales)
Oct 2035
Zenobe Little Horsted BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Zenobe Necton BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Necton 400kV Substation
National Grid (England & Wales)
Oct 2034
Zenobe Spennymoor BESS
Battery storage · Zenobe Energy Limited
300 MWScoping Wearside Connection Node D 400kV Substation
National Grid (England & Wales)
Oct 2035
Zenobe Yaxley BESS
Battery storage · Zenobe Energy Limited
300 MWScoping North Anglia Connection Node E 400kV Substation
National Grid (England & Wales)
Oct 2034
VPI Immingham B OCGT
Gas · Vpi Immingham B Limited
299 MWScoping Humber Refinery 400kV Substation
National Grid (England & Wales)
Jan 2026
Galileo 09
Solar + storage · Galileo 09 Limited
297 MWScoping Mid Wales Connection Node A 400Kv Substation
National Grid (England & Wales)
Oct 2037
Alcemi Ridham Docks BESF
Battery storage · Alcemi Storage Developments 23 Ltd
280 MWScoping North Kent Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2033
Buckland Marsh Solar Park
Solar + storage · Arise Renewable Energy UK Limited
280 MWScoping Botley West 400kV Substation
National Grid (England & Wales)
Oct 2033
Cellarhead Home Farm
Battery storage · Cellarhead BESS Ltd
280 MWScoping Cellarhead 132kV Substation
National Grid (England & Wales)
Oct 2028
Strawberry Farm
Battery storage · Qair Renewables UK Limited
278 MWScoping North Anglia Connection Node D 132kV Substation
National Grid (England & Wales)
Oct 2034
Lebanon Farm 2 BESS
Battery storage · Cedartech Energy Ltd
275 MWScoping Warley 275kV Substation
National Grid (England & Wales)
Oct 2030
Nant Mithil Energy Park
Onshore wind · Nant Mithil Energy Park Limited
253 MWScoping Pont Abraham 132KV
National Grid (England & Wales)
Oct 2026
Elmya Braybrooke BESS
Battery storage · Elmya Rpc UK Braybrooke Limited
252 MWAwaiting Consents Braybrooke 400kV Substation
National Grid (England & Wales)
Oct 2031
Page 10 of 20

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.