Grid infrastructure › Connection queue › Offshore wind

OFFSHORE WIND · NGET

Petroc Offshore Wind Farm

Petroc Offshore Wind Farm is a 300 MW offshore wind project in planning, connecting to the National Grid (England & Wales) network at Alverdiscott 400kV Substation, with capacity due from March 2029. The connection agreement is held by Bluefloat Energy UK Holdings Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Mar 2029 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001661
Customer
Bluefloat Energy UK Holdings Limited
Technology
Wind Offshore
Total capacity
300 MW
Change in this agreement
+300 MW
Capacity effective from
31 March 2029
Connection site
Alverdiscott 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Alverdiscott · Grid map

Other projects at Alverdiscott 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem