Zenobe Yaxley BESS is a 300 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at North Anglia Connection Node E 400kV Substation, with capacity due from October 2034. The connection agreement is held by Zenobe Energy Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2034 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-004088
Customer
Zenobe Energy Limited
Technology
Energy Storage System
Total capacity
300 MW
Change in this agreement
+300 MW
Capacity effective from
31 October 2034
Connection site
North Anglia Connection Node E 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

This project connects at a new substation (a “connection node”) that has not been built or located yet.

Projects connecting near North Anglia Connection Node E · Grid map

Other projects at North Anglia Connection Node E 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem