Larrea Solar

Larrea Solar is a 232 MW solar request in interconnection study in the ERCOT interconnection queue, in Pecos County, Texas.

Queue statusIn planning
  1. PlanningQueued Jan 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0146
Grid region
ERCOT (Texas)
Developer
Greasewood IV LLC
Connection point (POI)
Tap 345kV 76002 Bakerfield - 60404 Solstice CKT#1
Location
Pecos County, Texas
Technology
Solar: 232 MW
Total requested
232 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
3 January 2024
Proposed online date
September 2027

Location

Marker shows the centre of Pecos County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Pecos County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem