SOLAR Β· MISOSolar project J1129, Rock County
Solar project J1129, Rock County is a 65.0 MW solar request withdrawn in the MISO interconnection queue, in Rock County, Wisconsin, connecting to American Transmission Co..
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1129
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Paddock - Townline Rd 138 kV Line Tap
- Location
- Rock County, Wisconsin
- Technology
- Solar: 65.0 MW
- Total requested
- 65.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- January 2021
- Withdrawn
- October 2019
Location
Marker shows the centre of Rock County; the queue data does not give exact sites.
Power plants in Wisconsin Β· Transmission lines in Wisconsin
Other requests in Rock County
- Solar project J1460, Rock CountySolar Β· 200 MW Β· under construction
- Solar project J1377, Rock CountySolar Β· 98.6 MW Β· agreement signed
- Gas project J2947, Rock CountyGas Β· 205 MW Β· in study
- Battery storage project J3162, Rock CountyBattery storage Β· 100 MW Β· in study
- Gas project J3156, Rock CountyGas Β· 100 MW Β· in study
- Solar project J4097, Rock CountySolar Β· 71.5 MW Β· in study
- Surplus; J1304Other Β· 33.0 MW Β· in study
- Surplus; J1188Other Β· 25.0 MW Β· in study
- Gas project J390, Rock CountyGas Β· 711 MW Β· built
- Gas project G035, Rock CountyGas Β· 505 MW Β· built
- Solar project J850, Rock CountySolar Β· 250 MW Β· built
- Gas project G072, Rock CountyGas Β· 150 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem