SOLAR Β· ERCOT

Signal Solar

Signal Solar is a 51.8 MW solar request built and operating in the ERCOT interconnection queue, in Hunt County, Texas.

Queue statusOperating
  1. PlanningQueued Nov 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0208
Grid region
ERCOT (Texas)
Location
Hunt County, Texas
Technology
Solar: 51.8 MW
Total requested
51.8 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
6 November 2018
Came online
July 2025

Location

Marker shows the centre of Hunt County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas