🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Maryland

SOLAR · PJM

CleanLight Power Solar Facility

CleanLight Power Solar Facility is a 10.9 MW solar request withdrawn in the PJM interconnection queue, in Garrett County, Maryland, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2015 (completed)
  2. Withdrawn / abandonedNov 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB1-065
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Jennings-Hoyes 34.5kV
Location
Garrett County, Maryland
Technology
Solar: 10.9 MW
Total requested
10.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Withdrawn
Entered queue
31 August 2015
Proposed online date
October 2019
Withdrawn
November 2020

Location

Marker shows the centre of Garrett County; the queue data does not give exact sites.

Power plants in Maryland · Transmission lines in Maryland

Other requests in Garrett County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem