United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in the USA (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9118.5 GW
Active in queue18.5 GW91 requests
Agreement signed0.0 MW0 requests
Withdrawn101,304 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

91 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q617, Mohave County
Other
1,000 MWIn study Mohave, AZWest May 2025target 2031
Other project Q591, Maricopa County
Other
535 MWIn study Maricopa, AZWest May 2025target 2030
Other project Q580, Maricopa County
Other
500 MWIn study Maricopa, AZWest May 2025target 2032
Other project Q616, Maricopa County
Other
500 MWIn study Maricopa, AZWest May 2025target 2030
Other project Q603, Yuma County
Other
500 MWIn study Yuma, AZWest May 2025target 2030
Other project Q599, Yuma County
Other
500 MWIn study Yuma, AZWest May 2025target 2031
Other project Q609, Navajo County
Other
500 MWIn study Navajo, AZWest May 2025target 2026
Other project GEN-2025-SR9, Muskogee County
Other
410 MWIn study Muskogee, OKSPP May 2025target 2029
Other project Q581, Maricopa County
Other
400 MWIn study Maricopa, AZWest May 2025target 2031
Other project SC1Q31, Sacramento County
Other
400 MWIn study Sacramento, CAWest Jul 2025target 2032
Other project Q589, Pinal County
Other
400 MWIn study Pinal, AZWest May 2025target 2030
Other project Q606, Maricopa County
Other
350 MWIn study Maricopa, AZWest May 2025target 2030
Other project Q615, Maricopa County
Other
330 MWIn study Maricopa, AZWest May 2025target 2027
Other project Q596, Yuma County
Other
330 MWIn study Yuma, AZWest May 2025target 2029
Other project 771, Baker County
Other
325 MWIn study Baker, ORWest Apr 2025target 2029
Other project 977298, Wake County
Other
300 MWIn study Wake, NCSoutheast Jun 2025
Other project Q597, Yuma County
Other
300 MWIn study Yuma, AZWest May 2025target 2029
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Other project Q586, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00041, Wake County
Other
300 MWIn study Wake, NCSoutheast Aug 2025target 2030
Surplus; EAI.AECCO SWCT1
Other
300 MWIn study Lonoke, ARMISO Jun 2025target 2028
Other project Q578, Pinal County
Other
300 MWIn study Pinal, AZWest Apr 2025target 2029
Other project Q607, Maricopa County
Other
300 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q582, Maricopa County
Other
275 MWIn study Maricopa, AZWest May 2025target 2030
Other project PP00046, Richmond County
Other
275 MWIn study Richmond, NCSoutheast Aug 2025target 2029
Other project SC1Q33, Sacramento County
Other
250 MWIn study Sacramento, CAWest Jul 2025target 2030
Other project Q593, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q595, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q594, Pinal County
Other
250 MWIn study Pinal, AZWest May 2025target 2029
Other project Q618, Pima County
Other
250 MWIn study Pima, AZWest May 2025target 2030
Other project Q598, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Other project Q610, San Juan County
Other
250 MWIn study San Juan, NMWest May 2025target 2029
Other project GEN-2025-SR10, Seminole County
Other
238 MWIn study Seminole, OKSPP May 2025target 2030
Other project GEN-2025-SR25, Tulsa County
Other
200 MWIn study Tulsa, OKSPP Jun 2025target 2028
Surplus; J834
Other
200 MWIn study Phillips, ARMISO Feb 2025target 2027
Other project 37681, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Other project GEN-2025-SR24, Washington County
Other
200 MWIn study Washington, NESPP Jun 2025target 2028
Other project GEN-2025-SR26, Cass County
Other
200 MWIn study Cass, NESPP Jun 2025target 2029
Other project 38047, Platte County
Other
200 MWIn study Platte, WYWest Jul 2025target 2029
Other project Q585, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2030
Other project Q605, Maricopa County
Other
200 MWIn study Maricopa, AZWest May 2025target 2031
Other project Q604, Pinal County
Other
200 MWIn study Pinal, AZWest May 2025target 2030
Other project 38412, Goshen County
Other
200 MWIn study Goshen, WYWest Jul 2025target 2029
Other project PP00048, Onslow County
Other
199 MWIn study Onslow, NCSoutheast Aug 2025target 2030
Other project 977328, Robeson County
Other
199 MWIn study Robeson, NCSoutheast Jun 2025
Other project PP00047, Robeson County
Other
199 MWIn study Robeson, NCSoutheast Aug 2025target 2030
Other project PP00049, Onslow County
Other
199 MWIn study Onslow, NCSoutheast Aug 2025target 2030
Other project Q590, Maricopa County
Other
180 MWIn study Maricopa, AZWest May 2025target 2028
Other project Q612, Coconino County
Other
161 MWIn study Coconino, AZWest May 2025target 2028
Surplus; J1450
Other
150 MWIn study Webster, KYMISO Feb 2025target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)