United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESNuclear withdrawn queue requests in the USA
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Comanche Peak 3 and 4 Nuclear ยท TXU Generation |
3,200 MW | Withdrawn / abandoned |
| Victoria City Nuclear Nuclear ยท Exelon Generation Company, LLC |
3,200 MW | Withdrawn / abandoned |
| Bay City Nuclear Station Nuclear ยท Exelon Power Team |
3,200 MW | Withdrawn / abandoned |
| Nuclear project 205, Jackson County Nuclear |
2,772 MW | Withdrawn / abandoned |
| STP 3 and 4 Nuclear ยท STP Nuclear Operating Company |
2,700 MW | Withdrawn / abandoned |
| Nuclear project 206, Jackson County Nuclear |
2,476 MW | Withdrawn / abandoned |
| Nuclear project J371, Ogle County Nuclear |
2,325 MW | Withdrawn / abandoned |
| Nuclear project 211, Jackson County Nuclear |
2,234 MW | Withdrawn / abandoned |
| Nuclear project 212, Jackson County Nuclear |
2,234 MW | Withdrawn / abandoned |
| Nuclear project G0869, Benton County Nuclear |
2,200 MW | Withdrawn / abandoned |
| Nine Mile Point Station Unit #3 Nuclear ยท UniStar Nuclear Energy |
1,660 MW | Withdrawn / abandoned |
| Nuclear project G733, Callaway County Nuclear |
1,650 MW | Withdrawn / abandoned |
| Nuclear project V2-042, Calvert County Nuclear |
1,640 MW | Withdrawn / abandoned |
| Nuclear project Q77, Calvert County Nuclear |
1,640 MW | Withdrawn / abandoned |
| Calvert Cliffs Nuclear Power Plant Unit 3 Nuclear |
1,640 MW | Withdrawn / abandoned |
| North Anna Power Station Unit 3 Nuclear |
1,594 MW | Withdrawn / abandoned |
| Nuclear project G867, Monroe County Nuclear |
1,563 MW | Withdrawn / abandoned |
| Nuclear project 234, Jackson County Nuclear |
1,480 MW | Withdrawn / abandoned |
| Nuclear project J372, Rock Island County Nuclear |
1,373 MW | Withdrawn / abandoned |
| Nuclear project 217, Jackson County Nuclear |
1,250 MW | Withdrawn / abandoned |
| Nuclear project 46, Levy County Nuclear ยท Duke Energy Florida, LLC |
1,150 MW | Withdrawn / abandoned |
| Nuclear project 104, Levy County Nuclear ยท Duke Energy Florida, LLC |
1,150 MW | Withdrawn / abandoned |
| Nuclear project 32, Levy County Nuclear ยท Duke Energy Florida, LLC |
1,150 MW | Withdrawn / abandoned |
| Nuclear project 8, Sumter County Nuclear ยท Duke Energy Florida, LLC |
1,150 MW | Withdrawn / abandoned |
| Nuclear project 41400, Wake County Nuclear ยท Duke Energy Progress, LLC |
1,125 MW | Withdrawn / abandoned |
| Nuclear project 41638, Anson County Nuclear ยท Masked |
937 MW | Withdrawn / abandoned |
| Nuclear project J649, Dauphin County Nuclear |
829 MW | Withdrawn / abandoned |
| Nuclear project R01, Montour County Nuclear |
800 MW | Withdrawn / abandoned |
| Nuclear project R02, Luzerne County Nuclear |
800 MW | Withdrawn / abandoned |
| Nuclear project 240, Anderson County Nuclear |
720 MW | Withdrawn / abandoned |
| Linn County Generating Facility Nuclear ยท NextEra Energy Resources Development, LLC |
676 MW | Withdrawn / abandoned |
| Nuclear project 1065, Butte County Nuclear |
600 MW | Withdrawn / abandoned |
| Nuclear project TCS-11, Butte County Nuclear |
462 MW | Withdrawn / abandoned |
| Nuclear project Y1-005, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| Nuclear project W1-040, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| Nuclear project J123, Goodhue County Nuclear |
200 MW | Withdrawn / abandoned |
| Nuclear project GEN-2008-124N Nuclear |
165 MW | Withdrawn / abandoned |
| Nuclear project 41, Citrus County Nuclear ยท Duke Energy Florida, LLC |
140 MW | Withdrawn / abandoned |
| Nuclear project GEN-2012-017, Nemaha County Nuclear |
115 MW | Withdrawn / abandoned |
| FitzPatrick Nuclear Uprate Nuclear ยท FitzPatrick Nuclear Station |
112 MW | Withdrawn / abandoned |
| Nuclear project GEN-2007-030O, Washington County Nuclear |
67.0 MW | Withdrawn / abandoned |
| Nuclear project X3-056, Luzerne County Nuclear |
50.0 MW | Withdrawn / abandoned |
| Nuclear project AF2-315, Luzerne County Nuclear |
50.0 MW | Withdrawn / abandoned |
| Nuclear project AF2-251, Luzerne County Nuclear |
50.0 MW | Withdrawn / abandoned |
| Nuclear project X3-057, Luzerne County Nuclear |
50.0 MW | Withdrawn / abandoned |
| Songs High Pressure Turbine Retrofit Nuclear |
48.0 MW | Withdrawn / abandoned |
| Nuclear project A54, Dauphin County Nuclear |
45.0 MW | Withdrawn / abandoned |
| Nuclear project K27, Calvert County Nuclear |
35.0 MW | Withdrawn / abandoned |
| Nuclear project X3-045, Grundy County Nuclear |
32.0 MW | Withdrawn / abandoned |
| Nuclear project X3-046, Rock Island County Nuclear |
32.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- Southeast (non-ISO utilities)18 ยท 20.0 GW
- ERCOT (Texas)4 ยท 12.3 GW
- PJM (Mid-Atlantic, Midwest)24 ยท 9,262 MW
- MISO (Midcontinent)11 ยท 8,701 MW
- West (non-ISO utilities)3 ยท 3,262 MW
- NYISO (New York)2 ยท 1,772 MW
- SPP (Southwest Power Pool)3 ยท 347 MW
- CAISO (California)2 ยท 76.0 MW
- ISO-NE (New England)1 ยท 29.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)