United States โ€บ Grid โ€บ Interconnection queues โ€บ Pennsylvania

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown494,265 MW
Active in queue390 MW7 requests
Agreement signed59.8 MW3 requests
Withdrawn494,265 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

49 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Other project AE1-234, Chester County
Other
578 MWWithdrawn / abandoned Chester, PAPJM Sep 2018
Renovo Energy Center Uprate
Gas ยท Renovo Energy Center, LLC
548 MWWithdrawn / abandoned Clinton, PANYISO Feb 2018
Hydro project AE1-058, Schuylkill County
Hydro
500 MWWithdrawn / abandoned Schuylkill, PAPJM Jul 2018target 2022
South Bend Generating Station
Gas
410 MWWithdrawn / abandoned Armstrong, PAPJM Mar 2018target 2023
Battery storage project AD2-050, Bucks County
Battery storage
200 MWWithdrawn / abandoned Bucks, PAPJM Jan 2018target 2019
AREW Old Forge
Hydro
200 MWWithdrawn / abandoned Luzerne, PAPJM Jul 2018target 2027
Onshore wind project AD2-196, Luzerne County
Onshore wind
150 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2018target 2020
Onshore wind project AD2-152, Wayne County
Onshore wind
150 MWWithdrawn / abandoned Wayne, PAPJM Mar 2018target 2020
Solar project AD2-120, Mercer County
Solar
120 MWWithdrawn / abandoned Mercer, PAPJM Mar 2018target 2020
Solar + storage project AE1-128, Bedford County
Solar + storage
120 MWWithdrawn / abandoned Bedford, PAPJM Sep 2018target 2021
Solar project AE1-224, Montour County
Solar
100 MWWithdrawn / abandoned Montour, PAPJM Sep 2018target 2020
Solar project AE1-132, Fulton County
Solar
85.0 MWWithdrawn / abandoned Fulton, PAPJM Sep 2018target 2021
Solar project AE1-169, Venango County
Solar
85.0 MWWithdrawn / abandoned Venango, PAPJM Sep 2018target 2021
Gas project AE1-080, Washington County
Gas
80.0 MWWithdrawn / abandoned Washington, PAPJM Aug 2018target 2022
Solar project AD2-119, Centre County
Solar
75.0 MWWithdrawn / abandoned Centre, PAPJM Mar 2018target 2021
Solar project AE1-131, Adams County
Solar
65.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2021
Solar project AE1-139, Adams County
Solar
65.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2022
Solar + storage project AE1-141, Mercer County
Solar + storage
55.0 MWWithdrawn / abandoned Mercer, PAPJM Sep 2018target 2021
Solar project AE1-136, Franklin County
Solar
53.3 MWWithdrawn / abandoned Franklin, PAPJM Sep 2018target 2021
Solar project AE1-127, Northumberland County
Solar
50.0 MWWithdrawn / abandoned Northumberland, PAPJM Sep 2018target 2021
Other project AE1-253, Adams County
Other
50.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2020
Solar project AE1-181, Luzerne County
Solar
45.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2018target 2020
Renovo Energy Center
Gas
44.0 MWWithdrawn / abandoned Clinton, PAPJM Feb 2018target 2025
Solar project AE1-239, Mercer County
Solar
38.2 MWWithdrawn / abandoned Mercer, PAPJM Sep 2018target 2021
Solar project AE1-138, Adams County
Solar
22.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018
Solar project AE1-140, Franklin County
Solar
22.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2018target 2021
Solar project AE1-186, Berks County
Solar
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2018target 2021
Titusville Solar
Solar
20.0 MWWithdrawn / abandoned Venango, PAPJM Sep 2018target 2024
Brookview Solar I
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Apr 2018target 2025
Battery storage project AD2-125, Somerset County
Battery storage
20.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2018target 2020
Fayetteville Solar
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2018target 2022
Nittany Solar
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2018target 2022
Solar project AE1-165, Cambria County
Solar
20.0 MWWithdrawn / abandoned Cambria, PAPJM Sep 2018target 2021
Battery storage project AD2-127, Wayne County
Battery storage
20.0 MWWithdrawn / abandoned Wayne, PAPJM Mar 2018target 2020
Solar project AE1-187, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Sep 2018target 2021
Battery storage project AE1-202, Monroe County
Battery storage
19.8 MWWithdrawn / abandoned Monroe, PAPJM Sep 2018target 2020
Holtwood Solar
Solar
19.8 MWWithdrawn / abandoned Lancaster, PAPJM Sep 2018target 2026
Sunbury Solar
Solar
19.8 MWWithdrawn / abandoned Snyder, PAPJM Sep 2018target 2027
Battery storage project AD2-128, Fayette County
Battery storage
15.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2018target 2020
Solar project AD2-117, Berks County
Solar
15.0 MWWithdrawn / abandoned Berks, PAPJM Mar 2018target 2020
Gas project AD2-109, Fayette County
Gas
12.0 MWWithdrawn / abandoned Fayette, PAPJM Mar 2018target 2022
Other project AE2-009, Adams County
Other
11.0 MWWithdrawn / abandoned Adams, PAPJM Oct 2018target 2020
Solar project AE1-182, Cumberland County
Solar
10.0 MWWithdrawn / abandoned Cumberland, PAPJM Sep 2018
Battery storage project AD2-161, Luzerne County
Battery storage
10.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2018target 2022
Battery storage project AD2-129, Somerset County
Battery storage
9.0 MWWithdrawn / abandoned Somerset, PAPJM Mar 2018target 2020
Battery storage project AE1-029, Mercer County
Battery storage
8.8 MWWithdrawn / abandoned Mercer, PAPJM May 2018target 2019
Battery storage project AD2-217, Mercer County
Battery storage
8.8 MWWithdrawn / abandoned Mercer, PAPJM Mar 2018target 2019
Gas project AD2-111, Luzerne County
Gas
8.0 MWWithdrawn / abandoned Luzerne, PAPJM Mar 2018target 2022
Solar project AD2-061, Adams County
Solar
7.4 MWWithdrawn / abandoned Adams, PAPJM Feb 2018target 2020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)