Other project AE1-234, Chester County

Other project AE1-234, Chester County is a 578 MW other request withdrawn in the PJM interconnection queue, in Chester County, Pennsylvania, connecting to PECO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2018 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-234
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PECO
Connection point (POI)
Nottingham 230kV Reactor Bypass
Location
Chester County, Pennsylvania
Technology
Other: 578 MW
Total requested
578 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
27 September 2018
Withdrawn
October 2018

Location

Marker shows the centre of Chester County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Chester County