BATTERY STORAGE Β· PJM

Battery storage project AD2-125, Somerset County

Battery storage project AD2-125, Somerset County is a 20.0 MW battery storage request withdrawn in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedApr 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AD2-125
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Myersdale Storage
Location
Somerset County, Pennsylvania
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
23 March 2018
Proposed online date
December 2020
Withdrawn
April 2018

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem