Withdrawn queue requests in Oklahoma (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown223,239 MW
Active in queue220 MW1 requests
Agreement signed220 MW1 requests
Withdrawn223,239 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

22 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GEN-2015-038, Canadian County
Onshore wind
304 MWWithdrawn / abandoned Canadian, OKSPP Sep 2015target 2017
Onshore wind project GEN-2015-060, Ellis County
Onshore wind
251 MWWithdrawn / abandoned Ellis, OKSPP Oct 2015target 2021
Onshore wind project GEN-2015-093, Caddo County
Onshore wind
250 MWWithdrawn / abandoned Caddo, OKSPP Sep 20152025
Onshore wind project GEN-2015-092, Grady County
Onshore wind
250 MWWithdrawn / abandoned Grady, OKSPP Sep 20152020
Onshore wind project GEN-2015-030, Noble County
Onshore wind
200 MWWithdrawn / abandoned Noble, OKSPP Mar 20152017
Onshore wind project GEN-2015-086, Woodward County
Onshore wind
200 MWWithdrawn / abandoned Woodward, OKSPP Sep 2015target 2018
Onshore wind project GEN-2015-049, Dewey County
Onshore wind
200 MWWithdrawn / abandoned Dewey, OKSPP Oct 2015target 2018
Onshore wind project GEN-2015-003, Grant County
Onshore wind
200 MWWithdrawn / abandoned Grant, OKSPP Mar 2015target 2017
Onshore wind project GEN-2015-071, Beckham County
Onshore wind
200 MWWithdrawn / abandoned Beckham, OKSPP Oct 20152021
Solar project GEN-2015-002, Canadian County
Solar
200 MWWithdrawn / abandoned Canadian, OKSPP Mar 2015target 2018
Onshore wind project GEN-2015-081, Dewey County
Onshore wind
180 MWWithdrawn / abandoned Dewey, OKSPP Sep 2015target 2018
Onshore wind project GEN-2015-095, Woods County
Onshore wind
176 MWWithdrawn / abandoned Woods, OKSPP Sep 20152020
Onshore wind project GEN-2015-029, Dewey County
Onshore wind
161 MWWithdrawn / abandoned Dewey, OKSPP Mar 20152020
Solar project GEN-2015-067, Noble County
Solar
150 MWWithdrawn / abandoned Noble, OKSPP Oct 2015target 2017
Solar project GEN-2015-085, Jackson County
Solar
122 MWWithdrawn / abandoned Jackson, OKSPP Sep 2015target 2018
Onshore wind project GEN-2015-004, Beckham County
Onshore wind
52.9 MWWithdrawn / abandoned Beckham, OKSPP Mar 20152020
Solar project GEN-2015-084, Harmon County
Solar
51.3 MWWithdrawn / abandoned Harmon, OKSPP Sep 2015target 2018
Solar project GEN-2015-055, Beckham County
Solar
40.0 MWWithdrawn / abandoned Beckham, OKSPP Oct 20152024
Gas project GEN-2015-035, Kay County
Gas
22.0 MWWithdrawn / abandoned Kay, OKSPP Sep 2015target 2018
Battery storage project GEN-2015-044, Caddo County
Battery storage
20.0 MWWithdrawn / abandoned Caddo, OKSPP Oct 2015target 2017
Onshore wind project GEN-2015-059, Grady County
Onshore wind
6.3 MWWithdrawn / abandoned Grady, OKSPP Oct 2015target 2016
Onshore wind project GEN-2015-028, Kay County
Onshore wind
3.0 MWWithdrawn / abandoned Kay, OKSPP Apr 2015target 2016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)