United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Ohio (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown263,146 MW
Active in queue3,146 MW26 requests
Agreement signed2,650 MW22 requests
Withdrawn576,262 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

26 requests
ProjectCapacityStatusLocationRegionQueuedOnline
West Lorain Power Plant 345 kV
Gas
406 MWAgreement signed Lorain, OHPJM Sep 2020target 2031
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Butterfly Meadows
Solar Β· Butterfly Meadows Solar Project, LLC
300 MWIn study Van Wert, OHPJM Sep 2020target 2024
Palomino Solar
Solar
150 MWAgreement signed Highland, OHPJM Aug 2020target 2027
South Branch Solar
Solar
130 MWAgreement signed Hancock, OHPJM Mar 2020target 2026
Harvey Solar I
Solar
128 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Canal Road
Solar
120 MWAgreement signed Wayne, OHPJM Mar 2020target 2027
Union Ridge Solar
Solar
108 MWAgreement signed Licking, OHPJM Feb 2020target 2026
Butterfly Meadows
Battery storage Β· Butterfly Meadows Solar Project, LLC
100 MWIn study Van Wert, OHPJM Sep 2020target 2024
Blossom Solar
Solar
88.0 MWAgreement signed Morrow, OHPJM Mar 2020target 2027
Harvey Solar I
Solar
85.0 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Prairie Flyer Energy Storage
Battery storage
85.0 MWAgreement signed Montgomery, OHPJM Sep 2020target 2028
Carnation
Solar
84.0 MWAgreement signed Fairfield, OHPJM Mar 2020target 2028
Frasier Solar
Solar
80.0 MWAgreement signed Knox, OHPJM Mar 2020target 2028
Carnation
Solar
58.0 MWAgreement signed Fairfield, OHPJM Sep 2020target 2028
Blossom Solar
Solar
56.0 MWAgreement signed Morrow, OHPJM Jun 2020target 2027
Scioty Solar
Solar
50.0 MWAgreement signed Hardin, OHPJM Sep 2020target 2027
Timber Road Storage III
Battery storage
50.0 MWAgreement signed Paulding, OHPJM Mar 2020target 2029
Palomino Solar
Solar
50.0 MWAgreement signed Highland, OHPJM Mar 2020target 2027
Paulding Storage II
Battery storage Β· Paulding Wind Farm II LLC
50.0 MWIn study Paulding, OHPJM Mar 2020target 2023
Timber Road Solar Park III
Solar
49.9 MWAgreement signed Paulding, OHPJM Sep 2020target 2029
Solar project AF2-298, Montgomery County
Solar
49.9 MWAgreement signed Montgomery, OHPJM Mar 2020target 2028
South Branch Solar
Solar
46.0 MWPaused / redesign Hancock, OHPJM Jul 2020target 2025
Juliet Energy
Solar Β· Juliet Energy Project, LLC
12.0 MWAgreement signed Wood, OHPJM Feb 2020target 2027
West Lorain 138 kV Power Plant
Gas
11.3 MWAgreement signed Lorain, OHPJM Sep 2020target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)