United States βΊ Grid βΊ Interconnection queues βΊ Ohio
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Ohio (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project AE2-149, Pickaway County Solar + storage |
400 MW | Withdrawn / abandoned |
| Birch Solar Solar |
300 MW | Withdrawn / abandoned |
| Solar project AF1-034, Highland County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project AE2-329, Clermont County Battery storage |
209 MW | Withdrawn / abandoned |
| Battery storage project AE2-300, Licking County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AF1-117, Ross County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project AE2-174, Seneca County Onshore wind |
198 MW | Withdrawn / abandoned |
| Solar project AF1-113, Auglaize County Solar |
180 MW | Withdrawn / abandoned |
| Eldean Solar Solar |
178 MW | Withdrawn / abandoned |
| Urbana Solar Solar |
151 MW | Withdrawn / abandoned |
| Solar + storage project AF1-279, Lorain County Solar + storage |
150 MW | Withdrawn / abandoned |
| Battery storage project AE2-331, Defiance County Battery storage |
139 MW | Withdrawn / abandoned |
| Gas project AF2-012, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Gas project AE2-296, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Solar project AF1-035, Highland County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AF1-076, Allen County Solar |
100 MW | Withdrawn / abandoned |
| Hayden Run Solar |
100 MW | Withdrawn / abandoned |
| Solar project AF1-077, Allen County Solar |
100 MW | Withdrawn / abandoned |
| Mustang County Solar Project Solar |
100 MW | Withdrawn / abandoned |
| Solar project AE2-180, Madison County Solar |
79.0 MW | Withdrawn / abandoned |
| Solar project AE2-179, Pike County Solar |
78.0 MW | Withdrawn / abandoned |
| Solar project AF1-085, Auglaize County Solar |
77.0 MW | Withdrawn / abandoned |
| Solar project AF1-308, Pike County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project AF1-315, Clermont County Solar |
60.0 MW | Withdrawn / abandoned |
| Solar project AF1-319, Union County Solar |
58.0 MW | Withdrawn / abandoned |
| Battery storage project AE2-327, Pickaway County Battery storage |
52.2 MW | Withdrawn / abandoned |
| Solar project AF1-247, Butler County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AF1-270, Logan County Solar Β· Fountain Point Solar Energy LLC |
50.0 MW | Withdrawn / abandoned |
| Solar project AE2-320, Pickaway County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AE2-073, Licking County Solar |
50.0 MW | Withdrawn / abandoned |
| Cardinal Solar Solar |
49.9 MW | Withdrawn / abandoned |
| Solar project AE2-302, Jackson County Solar |
49.9 MW | Withdrawn / abandoned |
| Solar project AF1-230, Crawford County Solar |
49.0 MW | Withdrawn / abandoned |
| Battery storage project AF1-047, Defiance County Battery storage |
34.8 MW | Withdrawn / abandoned |
| Solar project AF1-063, Defiance County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project AF1-029, Van Wert County Solar |
25.0 MW | Withdrawn / abandoned |
| Battery storage project AE2-324, Marion County Battery storage |
20.3 MW | Withdrawn / abandoned |
| Battery storage project AF2-033, Hamilton County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Robertsville PV I Solar |
19.7 MW | Withdrawn / abandoned |
| Bolivar Solar Solar |
19.3 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)