Solar project GEN-2018-043, Burt County Solar |
500 MW | Agreement signed |
Burt, NE | SPP |
May 2018 | target 2028 |
Solar project GEN-2020-084, Burt County Solar |
350 MW | Agreement signed |
Burt, NE | SPP |
Apr 2020 | target 2030 |
Onshore wind project BHBE G13, Custer County Onshore wind |
300 MW | Agreement signed |
Custer, NE | West |
Jul 2017 | target 2023 |
Onshore wind project GEN-2017-181, Lancaster County Onshore wind |
300 MW | Agreement signed |
Lancaster, NE | SPP |
Nov 2017 | target 2028 |
Gas project GEN-2020-038, Cass County Gas |
273 MW | Agreement signed |
Cass, NE | SPP |
Apr 2020 | target 2028 |
Gas project GEN-2020-031, Sarpy County Gas |
273 MW | Agreement signed |
Sarpy, NE | SPP |
Apr 2020 | target 2028 |
Battery storage project GEN-2021-043, Lancaster County Battery storage |
250 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2030 |
Solar project GEN-2020-094, Otoe County Solar |
250 MW | Agreement signed |
Otoe, NE | SPP |
Apr 2020 | target 2030 |
Onshore wind project GEN-2017-201, Wayne County Onshore wind |
250 MW | Agreement signed |
Wayne, NE | SPP |
Nov 2017 | target 2028 |
Onshore wind project GEN-2018-125, Lancaster County Onshore wind |
231 MW | Agreement signed |
Lancaster, NE | SPP |
Nov 2018 | target 2031 |
Solar project GEN-2021-049, Lancaster County Solar |
225 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2029 |
Solar project GEN-2018-131, Pierce County Solar |
221 MW | Agreement signed |
Pierce, NE | SPP |
Nov 2018 | target 2031 |
Solar project GEN-2018-132, Pierce County Solar |
202 MW | Agreement signed |
Pierce, NE | SPP |
Nov 2018 | target 2026 |
Onshore wind project GEN-2017-144, Holt County Onshore wind |
200 MW | Agreement signed |
Holt, NE | SPP |
Nov 2017 | target 2028 |
Onshore wind project GEN-2016-074, Custer County Onshore wind |
200 MW | Agreement signed |
Custer, NE | SPP |
Apr 2016 | target 2027 |
Solar project GEN-2019-039, Butler County Solar |
175 MW | Agreement signed |
Butler, NE | SPP |
May 2019 | target 2027 |
Onshore wind project GEN-2017-182, Lancaster County Onshore wind |
128 MW | Agreement signed |
Lancaster, NE | SPP |
Nov 2017 | target 2028 |
Onshore wind project GEN-2017-234, Greeley County Onshore wind |
115 MW | Agreement signed |
Greeley, NE | SPP |
Nov 2017 | 2024 |
Solar project GEN-2021-034, Lancaster County Solar |
113 MW | Agreement signed |
Lancaster, NE | SPP |
May 2021 | target 2030 |
Solar project GEN-2020-078, Washington County Solar |
100 MW | Agreement signed |
Washington, NE | SPP |
Apr 2020 | target 2022 |
Onshore wind project GEN-2017-105, Burt County Onshore wind |
75.0 MW | Agreement signed |
Burt, NE | SPP |
Jul 2017 | target 2026 |
Battery storage project GEN-2021-048, Lancaster County Battery storage |
75.0 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2021 | target 2029 |
Solar project GEN-2013-019, Lancaster County Solar |
73.6 MW | Agreement signed |
Lancaster, NE | SPP |
Apr 2013 | target 2026 |
Solar project GEN-2013-002, Lancaster County Solar |
50.6 MW | Agreement signed |
Lancaster, NE | SPP |
Mar 2013 | target 2026 |
Onshore wind project GEN-2018-060, Webster County Onshore wind |
50.0 MW | Agreement signed |
Webster, NE | SPP |
May 2018 | target 2026 |
Onshore wind project GEN-2016-075, Holt County Onshore wind |
50.0 MW | Agreement signed |
Holt, NE | SPP |
Mar 2016 | target 2027 |
Solar project GEN-2016-147, Cheyenne County Solar |
40.0 MW | Agreement signed |
Cheyenne, NE | SPP |
Nov 2016 | 2024 |
Other project GEN-2023-SR1, Brown County Other |
21.9 MW | Agreement signed |
Brown, NE | SPP |
Dec 2022 | 2024 |
Battery storage project GEN-2017-198, Douglas County Battery storage |
11.6 MW | Agreement signed |
Douglas, NE | SPP |
Nov 2017 | target 2027 |