United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in Michigan

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown202,305 MW
Active in queue2,305 MW20 requests
Agreement signed180 MW2 requests
Withdrawn328,158 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

20 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replacing 749 MW of coal generation with BESS; Campbell 3
Other
749 MWIn study Ottawa, MIMISO Nov 2023target 2028
Replacing 220 MW of coal generation with BESS; Trenton Channel 9
Other
220 MWIn study Wayne, MIMISO Oct 2023target 2025
Surplus; J1062
Other
150 MWIn study Washtenaw, MIMISO Oct 2024target 2027
Surplus; J875
Other
150 MWIn study Lenawee, MIMISO Oct 2024target 2027
Surplus; J1320
Other
150 MWIn study Branch, MIMISO Aug 2024target 2026
Surplus; J806
Other
149 MWIn study Calhoun, MIMISO target 2026
Surplus; J199/J202
Other
100 MWIn study Tuscola, MIMISO Jul 2024target 2013
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Surplus; J758
Other
100 MWIn study Calhoun, MIMISO Aug 2024target 2027
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J1224/J1329
Other
85.1 MWIn study Washtenaw, MIMISO Oct 2024target 2028
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Surplus; J928
Other
55.0 MWIn study Delta, MIMISO Apr 2022target 2025
Surplus; G905
Other
50.0 MWIn study Midland, MIMISO Aug 2024target 2026
Other project J3763, Wayne County
Other
7.5 MWIn study Wayne, MIMISO Apr 2024target 2026
Other project J646, Macomb County
Other
1.6 MWUnder construction Macomb, MIMISO Jun 2016target 2010
Other project L006, Otsego County
Other
-5.0 MWIn study Otsego, MIMISO Sep 2004target 2005
Other project L010
Other
-8.0 MWIn study MIMISO Apr 2005target 2005
Other project L003, Lenawee County
Other
-10.0 MWIn study Lenawee, MIMISO May 2004

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)