United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
OCTARY USA Β· INTERCONNECTION QUEUESBattery storage interconnection queue in Massachusetts
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery Storage Battery storage |
508 MW | Agreement signed |
| Battery Storage Battery storage |
500 MW | In study |
| Battery Storage Battery storage |
500 MW | In study |
| Battery Storage Battery storage |
350 MW | In study |
| Lite Brite Battery Storage Battery storage |
306 MW | Agreement signed |
| Battery Storage Battery storage |
300 MW | In study |
| Battery Storage Battery storage |
300 MW | In study |
| Battery Storage Battery storage |
290 MW | In study |
| Medway Grid Battery Storage Battery storage |
250 MW | Agreement signed |
| Battery Storage Battery storage |
250 MW | In study |
| Hecate Energy Eastern Ave Energy Center Battery storage |
250 MW | Agreement signed |
| Battery Storage Battery storage |
225 MW | In study |
| Norman Street Battery Storage Battery storage |
204 MW | Agreement signed |
| Battery Storage Battery storage |
204 MW | Agreement signed |
| Battery Storage Battery storage |
200 MW | In study |
| Battery Storage Battery storage |
180 MW | In study |
| Battery Storage Battery storage |
170 MW | In study |
| Battery Storage Battery storage |
170 MW | In study |
| Energy Storage Battery storage |
170 MW | Agreement signed |
| Battery Storage Battery storage |
168 MW | In study |
| Battery Storage Battery storage |
136 MW | In study |
| Battery Storage Battery storage |
125 MW | In study |
| Bear Swamp Unit 1 and 2 Upgrade Battery storage |
66.0 MW | Agreement signed |
| West Springfield 45 MW BESS Battery storage |
45.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)