United States βΊ Grid βΊ Interconnection queues βΊ Massachusetts
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Massachusetts (2024 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery Storage Battery storage |
408 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
366 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
254 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
251 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
205 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
153 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
150 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
142 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
134 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
116 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
105 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
101 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
101 MW | Withdrawn / abandoned |
| Battery Storage + Solar Solar + storage |
101 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
81.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
76.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
19.7 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
19.7 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
16.9 MW | Withdrawn / abandoned |
| HGE Group Study Battery storage |
13.0 MW | Withdrawn / abandoned |
| RMLD DER Group Study Battery storage |
10.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Walpole 146 110A - 2023 EE GB ASO Solar + storage |
5.0 MW | Withdrawn / abandoned |
| RMLD DER Group Study Battery storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Battery storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Battery storage |
5.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
5.0 MW | Withdrawn / abandoned |
| Canton 470 110A - 2023 EE GB ASO Battery storage |
5.0 MW | Withdrawn / abandoned |
| Medway 65 110A - 2023 EE GB ASO Battery storage |
4.9 MW | Withdrawn / abandoned |
| HGE Group Study Battery storage |
4.9 MW | Withdrawn / abandoned |
| HGE Group Study Gas |
4.0 MW | Withdrawn / abandoned |
| Medway 65 110B - 2023 EE GB ASO Solar + storage |
3.9 MW | Withdrawn / abandoned |
| Paxton BESS Battery storage |
3.0 MW | Withdrawn / abandoned |
| Sheld BESS Battery storage |
3.0 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
3.0 MW | Withdrawn / abandoned |
| TMLP Landfill Solar Solar |
3.0 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
2.8 MW | Withdrawn / abandoned |
| EE 2024 SEMA/Cape ASO Group Study Solar + storage |
2.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)