United States β€Ί Grid β€Ί Interconnection queues β€Ί Massachusetts

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Massachusetts

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown176,013 MW
Active in queue11.2 GW35 requests
Agreement signed6,013 MW17 requests
Withdrawn37048.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

17 requests
ProjectCapacityStatusLocationRegionQueuedOnline
SouthCoast Wind 1
Offshore wind
1,200 MWAgreement signed MAISO-NE Apr 2021target 2031
Bay State Wind 4 Offshore Wind
Offshore wind
1,200 MWAgreement signed MAISO-NE Dec 2019target 2033
Vineyard Offshore Wind
Offshore wind
800 MWAgreement signed MAISO-NE Nov 2016target 2026
Park City Offshore Wind
Offshore wind
791 MWAgreement signed MAISO-NE Dec 2017target 2029
Battery Storage
Battery storage
508 MWAgreement signed Middlesex, MAISO-NE Jun 2021target 2028
Lite Brite Battery Storage
Battery storage
306 MWAgreement signed Suffolk, MAISO-NE Jul 2021target 2028
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Hecate Energy Eastern Ave Energy Center
Battery storage
250 MWAgreement signed Suffolk, MAISO-NE Apr 2021target 2026
Norman Street Battery Storage
Battery storage
204 MWAgreement signed Middlesex, MAISO-NE Mar 2021target 2028
Battery Storage
Battery storage
204 MWAgreement signed Worcester, MAISO-NE Oct 2022target 2027
Energy Storage
Battery storage
170 MWAgreement signed Norfolk, MAISO-NE Apr 2019target 2027
Bear Swamp Unit 1 and 2 Upgrade
Battery storage
66.0 MWAgreement signed Berkshire, MAISO-NE Jan 2016target 2023
West Springfield 45 MW BESS
Battery storage
45.0 MWAgreement signed Hampden, MAISO-NE Jun 2022target 2029
Solar
Solar
6.8 MWAgreement signed Plymouth, MAISO-NE Jan 2018target 2019
Battery addition
Other
6.7 MWAgreement signed Franklin, MAISO-NE Aug 2021target 2027
Berkshire Wind Increase
Onshore wind
4.6 MWAgreement signed Berkshire, MAISO-NE Aug 2012target 2019
NEA Bell. Uprate (Northeast Energy Associates, LP)
Gas
1.4 MWAgreement signed Norfolk, MAISO-NE Mar 2015target 2018

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)