United States โบ Grid โบ Interconnection queues โบ Maryland
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Maryland (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project AC1-139, Frederick County Solar |
102 MW | Withdrawn / abandoned |
| Solar project AB2-120, Worcester County Solar |
100 MW | Withdrawn / abandoned |
| Potomac Solar, LLC Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project AC2-014, Charles County Solar |
32.5 MW | Withdrawn / abandoned |
| Solar project AB2-095, Wicomico County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project AC2-013, Charles County Solar |
27.5 MW | Withdrawn / abandoned |
| Solar project AC1-220, Queen Anne's County Solar |
26.5 MW | Withdrawn / abandoned |
| Solar project AB2-143, Kent County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-063, Queen Anne's County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-181, Frederick County Solar |
20.0 MW | Withdrawn / abandoned |
| Catoctin Furnace Solar Facility Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-183, Kent County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-182, Cecil County Solar |
20.0 MW | Withdrawn / abandoned |
| Hebron Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AB2-167, Worcester County Solar |
14.0 MW | Withdrawn / abandoned |
| Solar project AB2-144, Frederick County Solar |
13.8 MW | Withdrawn / abandoned |
| Solar project AB2-142, Caroline County Solar |
13.4 MW | Withdrawn / abandoned |
| Costen Solar Energy Center Solar |
10.0 MW | Withdrawn / abandoned |
| Crouse Solar Project Solar |
10.0 MW | Withdrawn / abandoned |
| Solar project AB2-056, Cecil County Solar |
10.0 MW | Withdrawn / abandoned |
| Funkstonw Solar Facility Solar |
8.8 MW | Withdrawn / abandoned |
| Solar project AB2-185, Queen Anne's County Solar |
8.0 MW | Withdrawn / abandoned |
| Solar project AB2-177, Worcester County Solar |
6.6 MW | Withdrawn / abandoned |
| Other project AC1-180, Somerset County Other |
6.0 MW | Withdrawn / abandoned |
| Aydelotte Solar Project Solar |
5.5 MW | Withdrawn / abandoned |
| Solar project AC1-213, Somerset County Solar |
5.3 MW | Withdrawn / abandoned |
| Mardela Springs Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AB2-184, Baltimore County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AC1-041, Worcester County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AB2-124, Howard County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AB2-123, Howard County Solar |
5.0 MW | Withdrawn / abandoned |
| Solar project AC1-049, Worcester County Solar |
4.0 MW | Withdrawn / abandoned |
| Other project AC1-177, Queen Anne's County Other |
4.0 MW | Withdrawn / abandoned |
| Other project AC1-028, Wicomico County Other |
3.8 MW | Withdrawn / abandoned |
| Solar project AB2-126, Baltimore County Solar |
3.8 MW | Withdrawn / abandoned |
| Solar project AB2-125, Anne Arundel County Solar |
3.3 MW | Withdrawn / abandoned |
| Harris Project Solar |
3.2 MW | Withdrawn / abandoned |
| Solar project AB2-140, Harford County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar project AC1-228, Dorchester County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar project AC2-005, Dorchester County Solar |
3.0 MW | Withdrawn / abandoned |
| Solar project AB2-118, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AB2-117, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AB2-113, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AB2-116, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AB2-115, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AB2-114, Cecil County Solar |
2.0 MW | Withdrawn / abandoned |
| Solar project AC1-031, Carroll County Solar |
2.0 MW | Withdrawn / abandoned |
| Battery storage project AC1-224, Talbot County Battery storage |
1.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)