πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR Β· PJM

Solar project AB2-095, Wicomico County

Solar project AB2-095, Wicomico County is a 30.0 MW solar request withdrawn in the PJM interconnection queue, in Wicomico County, Maryland, connecting to DPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedOct 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-095
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Ocean Pines-Walston Switch 69kV
Location
Wicomico County, Maryland
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
26 April 2016
Proposed online date
October 2018
Withdrawn
October 2016

Location

Marker shows the centre of Wicomico County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Wicomico County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem