Solar project AC2-013, Charles County

Solar project AC2-013, Charles County is a 27.5 MW solar request withdrawn in the PJM interconnection queue, in Charles County, Maryland, connecting to PEPCO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2016 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AC2-013
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PEPCO
Connection point (POI)
Ripley 69kV
Location
Charles County, Maryland
Technology
Solar: 27.5 MW
Total requested
27.5 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 December 2016
Proposed online date
November 2018
Withdrawn
January 2017

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.