πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

SOLAR Β· PJM

Solar project AB2-184, Baltimore County

Solar project AB2-184, Baltimore County is a 5.0 MW solar request withdrawn in the PJM interconnection queue, in Baltimore County, Maryland, connecting to BGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2016 (completed)
  2. Withdrawn / abandonedMay 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AB2-184
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
BGE
Connection point (POI)
Monkton
Location
Baltimore County, Maryland
Technology
Solar: 5.0 MW
Total requested
5.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
29 April 2016
Proposed online date
June 2017
Withdrawn
May 2016

Location

Marker shows the centre of Baltimore County; the queue data does not give exact sites.

Power plants in Maryland Β· Transmission lines in Maryland

Other requests in Baltimore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem