Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9517.0 GW
Active in queue6,766 MW33 requests
Agreement signed200 MW1 requests
Withdrawn9517.0 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

95 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2022-052, Bossier Parish County
Solar
850 MWWithdrawn / abandoned Bossier Parish, LASPP Jun 20222025
Solar + storage project J2911, Beauregard Parish County
Solar + storage
810 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Solar project J2706, Morehouse Parish County
Solar
500 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2027
Solar project J3032, Webster Parish County
Solar
500 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Solar project J2888, Lafayette Parish County
Solar
500 MWWithdrawn / abandoned Lafayette Parish, LAMISO Sep 2022target 2026
Solar + storage project J2890, Calcasieu Parish County
Solar + storage
440 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Sep 2022target 2027
Solar + storage project J2882, Beauregard Parish County
Solar + storage
410 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Solar project J2916, Rapides Parish County
Solar
400 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Battery storage project GEN-2022-051, Bossier Parish County
Battery storage
325 MWWithdrawn / abandoned Bossier Parish, LASPP Jun 20222025
Solar project J2508, Webster Parish County
Solar
300 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Solar + storage project J2884, Beauregard Parish County
Solar + storage
276 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Solar project J1953, Concordia Parish County
Solar
265 MWWithdrawn / abandoned Concordia Parish, LAMISO Jul 2022target 2025
Solar project J3197, Rapides Parish County
Solar
250 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Solar project J3055, Washington Parish County
Solar
250 MWWithdrawn / abandoned Washington Parish, LAMISO Sep 2022target 2027
Solar project J2505, Beauregard Parish County
Solar
250 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Solar project J2441, Beauregard Parish County
Solar
250 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Solar project J2348, Webster Parish County
Solar
225 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Solar project J2705, Assumption Parish County
Solar
220 MWWithdrawn / abandoned Assumption Parish, LAMISO Sep 2022target 2027
Battery storage project J2535, Vermilion Parish County
Battery storage
210 MWWithdrawn / abandoned Vermilion Parish, LAMISO Sep 2022target 2026
Solar project J2163, Calcasieu Parish County
Solar
200 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Jul 2022target 2024
Solar project J2035, Lafourche Parish County
Solar
200 MWWithdrawn / abandoned Lafourche Parish, LAMISO Apr 2022target 2025
Solar project J2942, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2025
Battery storage project J2570, Lafourche Parish County
Battery storage
200 MWWithdrawn / abandoned Lafourche Parish, LAMISO Sep 2022target 2026
Solar project J3067, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2025
Solar + storage project J3056, Washington Parish County
Solar + storage
200 MWWithdrawn / abandoned Washington Parish, LAMISO Sep 2022target 2027
Solar project J2860, Beauregard Parish County
Solar
200 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Solar project J2381, Union Parish County
Solar
200 MWWithdrawn / abandoned Union Parish, LAMISO Sep 2022target 2026
Battery storage project J2405, Jefferson Parish County
Battery storage
200 MWWithdrawn / abandoned Jefferson Parish, LAMISO Sep 2022target 2026
Solar project J2769, St. Helena Parish County
Solar
200 MWWithdrawn / abandoned St. Helena Parish, LAMISO Sep 2022target 2026
Battery storage project J2357, Lafourche Parish County
Battery storage
200 MWWithdrawn / abandoned Lafourche Parish, LAMISO Sep 2022target 2027
Solar project J3054, Washington Parish County
Solar
200 MWWithdrawn / abandoned Washington Parish, LAMISO Sep 2022target 2017
Solar project J2529, Rapides Parish County
Solar
200 MWWithdrawn / abandoned Rapides Parish, LAMISO Sep 2022target 2026
Solar project J2839, Ascension Parish County
Solar
200 MWWithdrawn / abandoned Ascension Parish, LAMISO Sep 2022target 2025
Solar + storage project J3019, East Feliciana Parish County
Solar + storage
180 MWWithdrawn / abandoned East Feliciana Parish, LAMISO Sep 2022target 2027
Solar project J2385, Franklin Parish County
Solar
179 MWWithdrawn / abandoned Franklin Parish, LAMISO Sep 2022target 2027
Battery storage project J2543, Beauregard Parish County
Battery storage
175 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Solar project J2743, Washington Parish County
Solar
175 MWWithdrawn / abandoned Washington Parish, LAMISO Sep 2022target 2026
Battery storage project J3026, Beauregard Parish County
Battery storage
175 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Solar project J2525, Morehouse Parish County
Solar
175 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2026
Battery storage project J2500, Beauregard Parish County
Battery storage
175 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2026
Battery storage project J2325, Morehouse Parish County
Battery storage
175 MWWithdrawn / abandoned Morehouse Parish, LAMISO Sep 2022target 2025
Solar project J2700, Calcasieu Parish County
Solar
170 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Sep 2022target 2027
Solar project J2968, Jefferson Davis Parish County
Solar
165 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Sep 2022target 2023
Solar project J2707, Assumption Parish County
Solar
165 MWWithdrawn / abandoned Assumption Parish, LAMISO Sep 2022target 2027
Solar + storage project J2904, Concordia Parish County
Solar + storage
150 MWWithdrawn / abandoned Concordia Parish, LAMISO Sep 2022target 2025
Solar project J2792, Concordia Parish County
Solar
150 MWWithdrawn / abandoned Concordia Parish, LAMISO Aug 2022target 2026
Battery storage project J2531, Union Parish County
Battery storage
140 MWWithdrawn / abandoned Union Parish, LAMISO Sep 2022target 2026
Battery storage project J2527, Allen Parish County
Battery storage
140 MWWithdrawn / abandoned Allen Parish, LAMISO Sep 2022target 2025
Battery storage project J2943, Webster Parish County
Battery storage
140 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Battery storage project J2479, Concordia Parish County
Battery storage
140 MWWithdrawn / abandoned Concordia Parish, LAMISO Sep 2022target 2025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)