United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Louisiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown183,056 MW
Active in queue37.6 GW140 requests
Agreement signed3,056 MW18 requests
Withdrawn31059.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

18 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1246, Iberville Parish County
Gas
725 MWAgreement signed Iberville Parish, LAMISO Apr 2019target 2025
Solar project J1598, Calcasieu Parish County
Solar
325 MWAgreement signed Calcasieu Parish, LAMISO Dec 2023target 2026
Solar project J1576, Washington Parish County
Solar
200 MWAgreement signed Washington Parish, LAMISO Mar 2022target 2026
Solar project J1431, St. James Parish County
Solar
200 MWAgreement signed St. James Parish, LAMISO Apr 2019target 2024
Solar project GEN-2018-050, Caddo Parish County
Solar
200 MWAgreement signed Caddo Parish, LASPP May 2018target 2028
Solar project J1583, Iberville Parish County
Solar
175 MWAgreement signed Iberville Parish, LAMISO Jun 2020target 2025
Solar project GEN-2018-106, Caddo Parish County
Solar
165 MWAgreement signed Caddo Parish, LASPP Nov 2018target 2028
Solar project J1465, Pointe Coupee Parish County
Solar
150 MWAgreement signed Pointe Coupee Parish, LAMISO Apr 2019target 2024
Solar project J1794, Acadia Parish County
Solar
150 MWAgreement signed Acadia Parish, LAMISO Jun 2020target 2025
Solar project J1542, St. James Parish County
Solar
135 MWAgreement signed St. James Parish, LAMISO Jun 2020target 2026
Gas project J1833, Lafourche Parish County
Gas
115 MWAgreement signed Lafourche Parish, LAMISO Oct 2021target 2025
Solar project J1564, Washington Parish County
Solar
100 MWAgreement signed Washington Parish, LAMISO Jun 2020target 2025
Solar project J1827, Morehouse Parish County
Solar
90.0 MWAgreement signed Morehouse Parish, LAMISO Oct 2021target 2026
Solar project J1818, Lafayette Parish County
Solar
80.0 MWAgreement signed Lafayette Parish, LAMISO Jun 2020target 2026
Solar project J1561, Acadia Parish County
Solar
75.0 MWAgreement signed Acadia Parish, LAMISO Oct 2021target 2026
Solar project GEN-2016-167, Caddo Parish County
Solar
73.5 MWAgreement signed Caddo Parish, LASPP Nov 20162024
Solar project GEN-2017-057, Caddo Parish County
Solar
72.5 MWAgreement signed Caddo Parish, LASPP May 20172025
Battery storage project J1602, Ouachita Parish County
Battery storage
25.0 MWAgreement signed Ouachita Parish, LAMISO Nov 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)