| Project | Capacity | Status |
|---|---|---|
| Solar project J1466, Henderson County Solar |
250 MW | Agreement signed |
| Lynn Bark Energy Center Solar |
200 MW | Agreement signed |
| Martin County Solar Project Solar |
190 MW | Paused / redesign |
| Fleming Solar Solar Β· AEUG Fleming Solar, LLC |
189 MW | Agreement signed |
| Solar project 364, Logan County Solar |
173 MW | Agreement signed |
| Solar project J1450, Webster County Solar |
150 MW | Agreement signed |
| Threeforks Energy Storage Battery storage |
100 MW | Agreement signed |
| Madison Solar 1 Solar Β· AEUG Madison Solar, LLC |
100 MW | In study |
| Solar project LGE-GIS-2019-025, Mercer County Solar |
99.0 MW | Agreement signed |
| Solar project 388, Simpson County Solar |
69.0 MW | Agreement signed |
| Mt Olive Creek Solar Solar |
60.0 MW | Agreement signed |
| Horseshoe Bend Solar Solar |
60.0 MW | Agreement signed |
| Flat Run Solar Solar |
55.0 MW | Agreement signed |
| Grassy Plains Solar |
40.0 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)9 Β· 994 MW
- MISO (Midcontinent)2 Β· 400 MW
- Southeast (non-ISO utilities)3 Β· 341 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)