Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown203,498 MW
Active in queue3,498 MW20 requests
Agreement signed743 MW6 requests
Withdrawn12729.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

20 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3910, Newton County
Onshore wind
300 MWIn study Newton, INMISO Feb 2025target 2030
Onshore wind project J4063, Knox County
Onshore wind
300 MWIn study Knox, INMISO Sep 2025target 2030
Onshore wind project J3564, Newton County
Onshore wind
275 MWIn study Newton, INMISO Apr 2024target 2028
Onshore wind project J3846, Newton County
Onshore wind
275 MWIn study Newton, INMISO Jan 2025target 2030
Vermilion Grove Wind
Onshore wind Β· Vermilion Grove Wind, LLC
255 MWIn study Vermillion, INPJM Sep 2019target 2022
Onshore wind project J1069, Jasper County
Onshore wind
200 MWUnder construction Jasper, INMISO Mar 2018target 2023
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Onshore wind project J2509, Tippecanoe County
Onshore wind
200 MWIn study Tippecanoe, INMISO Sep 2022target 2025
Prairie Creek Wind
Onshore wind Β· Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Teays River Wind Farm
Onshore wind Β· Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Onshore wind project J2654, Clinton County
Onshore wind
180 MWIn study Clinton, INMISO Sep 2022target 2026
Onshore wind project AI1-003, Huntington County
Onshore wind
170 MWIn study Huntington, INPJM Apr 2022target 2026
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Onshore wind project J2440, Benton County
Onshore wind
100 MWIn study Benton, INMISO Sep 2022target 2027
Prairie Creek Wind Phase 2
Onshore wind Β· Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Onshore wind project J2048, Benton County
Onshore wind
100 MWIn study Benton, INMISO Mar 2022target 2025
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Bitter Ridge Wind Farm
Onshore wind
12.6 MWAgreement signed Jay, INPJM May 2020target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)