Projects with signed interconnection agreements in Indiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6911.2 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

69 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J351, St. Joseph County
Gas
715 MWAgreement signed St. Joseph, INMISO May 2014target 2020
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Solar project J1308, Posey County
Solar
300 MWAgreement signed Posey, INMISO Apr 2019target 2024
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Black Prairie Solar Park
Solar
200 MWAgreement signed White, INPJM Sep 2019target 2027
Bottlebrush Solar
Solar
200 MWAgreement signed Lake, INPJM Jan 2019target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J1378, Fountain County
Solar
200 MWAgreement signed Fountain, INMISO Apr 2019target 2024
Prairie Creek Wind
Onshore wind ยท Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Lake Trout Solar
Solar + storage
200 MWAgreement signed Blackford, INPJM Sep 2019target 2028
Solar project J1381, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2026
Solar project J1348, Vermillion County
Solar
200 MWAgreement signed Vermillion, INMISO Apr 2019target 2025
Solar + storage project J1340, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1336, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Solar + storage project J1339, Jasper County
Solar + storage
200 MWAgreement signed Jasper, INMISO Apr 2019target 2025
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Solar project J643, Jasper County
Solar
175 MWAgreement signed Jasper, INMISO May 20162023
Battery storage project J1355, Laporte County
Battery storage
160 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Blackford Solar Energy Project
Solar
150 MWAgreement signed Jay, INPJM Sep 2019target 2026
Solar project J1027, Pike County
Solar
150 MWAgreement signed Pike, INMISO Mar 2018target 2022
Solar project J1482, White County
Solar
150 MWAgreement signed White, INMISO Apr 20192024
Solar project J1028, Pike County
Solar
150 MWAgreement signed Pike, INMISO Mar 2018target 2022
Riverstart Solar Park IV
Solar
150 MWAgreement signed Randolph, INPJM Sep 2017target 2025
Battery storage project J1357, Madison County
Battery storage
150 MWAgreement signed Madison, INMISO Apr 2019target 2025
Solar project J1388, Gibson County
Solar
150 MWAgreement signed Gibson, INMISO Apr 2019target 2024
Battery storage project J1354, Decatur County
Battery storage
146 MWAgreement signed Decatur, INMISO Apr 2019target 2025
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
Solar project J1393, Pike County
Solar
130 MWAgreement signed Pike, INMISO Apr 2019target 2026
Riverstart Solar Park II
Solar
125 MWAgreement signed Randolph, INPJM Mar 2019target 2027
Battery storage project J1358, Laporte County
Battery storage
125 MWAgreement signed Laporte, INMISO Apr 2019target 2026
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Rainbow Trout
Solar + storage
120 MWAgreement signed Tippecanoe, INPJM Sep 2020target 2028
Solar project J1234, Knox County
Solar
100 MWAgreement signed Knox, INMISO Apr 2019target 2023
Elkhart County Solar Project
Solar
100 MWAgreement signed Elkhart, INPJM Mar 2019target 2026
Solar project J1386, Lake County
Solar
100 MWAgreement signed Lake, INMISO Apr 2019target 2025
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Solar project J1407, Porter County
Solar
100 MWAgreement signed Porter, INMISO Apr 2019target 2025
Prairie Creek Wind Phase 2
Onshore wind ยท Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)