πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Illinois (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown214,337 MW
Active in queue4,337 MW21 requests
Agreement signed1,662 MW10 requests
Withdrawn5311.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

21 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Panther Grove 2
Onshore wind
300 MWAgreement signed Woodford, ILPJM Sep 2018target 2028
Livingston Wind
Onshore wind Β· Livingston Wind Project, LLC
255 MWIn study Livingston, ILPJM Sep 2018target 2021
Broomstick Solar Energy Centergy Center
Solar
210 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Onshore wind project J1115, Macon County
Onshore wind
200 MWUnder construction Macon, ILMISO Mar 2018target 2024
Blooming Grove Solar Energy Center
Solar
200 MWAgreement signed Livingston, ILPJM Sep 2018target 2028
Lower Crossing Wind
Onshore wind
200 MWPaused / redesign Kankakee, ILPJM Jan 2018target 2026
Osagrove Flats Wind
Onshore wind
150 MWAgreement signed Lasalle, ILPJM Jan 2018target 2026
Leaf River Wind
Onshore wind Β· Leaf River Wind, LLC
150 MWIn study Ogle, ILPJM Sep 2018target 2021
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Sep 2018target 2027
Solar project J1094, Washington County
Solar
150 MWUnder construction Washington, ILMISO Mar 2018target 2024
Solar project J1139, Champaign County
Solar
150 MWAgreement signed Champaign, ILMISO Mar 2018target 2023
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Shady Oaks Wind Power Project
Onshore wind
106 MWAgreement signed Lee, ILPJM Mar 2018target 2027
Solar project J1180, Clark County
Solar
75.0 MWUnder construction Clark, ILMISO Mar 20182024
Solar project J1102, Logan County
Solar
70.0 MWUnder construction Logan, ILMISO Mar 20182022
Broomstick Solar Energy Centergy Center
Solar
50.0 MWPaused / redesign Christian, ILPJM Mar 2018target 2028
Staley Solar
Solar
20.0 MWAgreement signed Kankakee, ILPJM Feb 2018target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)