United States โ€บ Grid โ€บ Interconnection queues โ€บ Illinois

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown670115.3 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

670 requests ยท page 1 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AE1-222, Grundy County
Gas
2,563 MWWithdrawn / abandoned Grundy, ILPJM Sep 2018target 2022
Nuclear project J371, Ogle County
Nuclear
2,325 MWWithdrawn / abandoned Ogle, ILMISO Jun 2014target 2016
Other project IP05, Randolph County
Other
1,500 MWWithdrawn / abandoned Randolph, ILMISO Dec 2001target 2010
Onshore wind project G902, Winnebago County
Onshore wind
1,500 MWWithdrawn / abandoned Winnebago, ILMISO Oct 2007target 2012
Nuclear project J372, Rock Island County
Nuclear
1,373 MWWithdrawn / abandoned Rock Island, ILMISO Jun 2014target 2019
Gas project AC1-153, Grundy County
Gas
1,300 MWWithdrawn / abandoned Grundy, ILPJM Oct 2016target 2021
Gas project AC1-067, Cook County
Gas
1,254 MWWithdrawn / abandoned Cook, ILPJM Sep 2016target 2021
Coal project Y2-095, Randolph County
Coal
1,211 MWWithdrawn / abandoned Randolph, ILPJM Oct 2012target 2013
Gas project AA2-035, Grundy County
Gas
1,019 MWWithdrawn / abandoned Grundy, ILPJM Dec 2014target 2019
Onshore wind project V4-074, Hancock County
Onshore wind
1,000 MWWithdrawn / abandoned Hancock, ILPJM Jan 2010target 2013
Coal project G367, Fulton County
Coal
800 MWWithdrawn / abandoned Fulton, ILMISO Oct 2003target 2007
Gas project J388, Vermilion County
Gas
800 MWWithdrawn / abandoned Vermilion, ILMISO Sep 2014target 2018
Gas project AA1-048, Grundy County
Gas
800 MWWithdrawn / abandoned Grundy, ILPJM Aug 2014target 2018
Coal project G661, Coles County
Coal
726 MWWithdrawn / abandoned Coles, ILMISO Jul 2006target 2007
Coal project Q68, Christian County
Coal
726 MWWithdrawn / abandoned Christian, ILPJM Jul 2006target 2015
Gas project J244, Christian County
Gas
726 MWWithdrawn / abandoned Christian, ILMISO May 2012target 2012
Gas project G500, Shelby County
Gas
710 MWWithdrawn / abandoned Shelby, ILMISO Feb 2005target 2005
Coal project H20_CE12, Adams County
Coal
700 MWWithdrawn / abandoned Adams, ILPJM Jan 2002target 2001
Coal project G529, Williamson County
Coal
650 MWWithdrawn / abandoned Williamson, ILMISO Jun 2005target 2011
Indeck-Elwood Energy Center
Coal
600 MWWithdrawn / abandoned Will, ILPJM Jul 2004target 2011
Gas project U2-095, Lee County
Gas
600 MWWithdrawn / abandoned Lee, ILPJM Jul 2008target 2011
Coal project V2-008, Christian County
Coal
600 MWWithdrawn / abandoned Christian, ILPJM May 2009target 2014
Onshore wind project G901, Winnebago County
Onshore wind
600 MWWithdrawn / abandoned Winnebago, ILMISO Oct 2007target 2010
Coal project Y2-116, Randolph County
Coal
600 MWWithdrawn / abandoned Randolph, ILPJM Nov 2012target 2013
Byron to Wayne Thermal #1 Project
Gas
575 MWWithdrawn / abandoned Lee, ILPJM Sep 2015target 2026
Gas project AB1-091, Kankakee County
Gas
575 MWWithdrawn / abandoned Kankakee, ILPJM Sep 2015target 2019
Gas project AB1-086, Mclean County
Gas
575 MWWithdrawn / abandoned Mclean, ILPJM Sep 2015target 2019
Gas project AB1-090, Lee County
Gas
575 MWWithdrawn / abandoned Lee, ILPJM Sep 2015target 2019
Coal project G476, Williamson County
Coal
545 MWWithdrawn / abandoned Williamson, ILMISO Oct 2004target 2004
Gas project G435, Williamson County
Gas
545 MWWithdrawn / abandoned Williamson, ILMISO Jul 2004target 2010
Other project J2697, St. Clair County
Other
500 MWWithdrawn / abandoned St. Clair, ILMISO Sep 2022target 2027
Onshore wind project AE1-193, Henry County
Onshore wind
500 MWWithdrawn / abandoned Henry, ILPJM Sep 2018target 2021
Onshore wind project S62, Lasalle County
Onshore wind
500 MWWithdrawn / abandoned Lasalle, ILPJM Jul 2007target 2016
Onshore wind project AE1-194, Will County
Onshore wind
500 MWWithdrawn / abandoned Will, ILPJM Sep 2018target 2021
Onshore wind project U2-058, Christian County
Onshore wind
500 MWWithdrawn / abandoned Christian, ILPJM Jun 2008target 2011
Battery storage project AG1-298, Cook County
Battery storage ยท Big Shoulders Storage LLC
500 MWWithdrawn / abandoned Cook, ILPJM Sep 2020target 2023
Onshore wind project AE1-195, Will County
Onshore wind
500 MWWithdrawn / abandoned Will, ILPJM Sep 2018target 2021
Other project IP12, Piatt County
Other
500 MWWithdrawn / abandoned Piatt, ILMISO Jul 2000target 2005
Pleasant Ridge Wind Farm
Onshore wind
500 MWWithdrawn / abandoned Livingston, ILPJM Oct 2006target 2020
Other project IP11, Washington County
Other
500 MWWithdrawn / abandoned Washington, ILMISO Jul 2000target 2006
Onshore wind project J038, Sangamon County
Onshore wind
498 MWWithdrawn / abandoned Sangamon, ILMISO Mar 2009target 2010
Gas project Z2-041, Mchenry County
Gas
455 MWWithdrawn / abandoned Mchenry, ILPJM Feb 2014target 2018
Onshore wind project W2-046, Livingston County
Onshore wind
450 MWWithdrawn / abandoned Livingston, ILPJM Jun 2010target 2013
Other project J1656, Vermilion County
Other
412 MWWithdrawn / abandoned Vermilion, ILMISO Jun 2020target 2023
Solar project J3965, Christian County
Solar
402 MWWithdrawn / abandoned Christian, ILMISO Apr 2025target 2030
Wind + storage project J2039, Sangamon County
Wind + storage
400 MWWithdrawn / abandoned Sangamon, ILMISO Aug 2021target 2024
Solar project J3349, Fulton County
Solar
400 MWWithdrawn / abandoned Fulton, ILMISO Apr 2024target 2028
Battery storage project J3728, Franklin County
Battery storage
400 MWWithdrawn / abandoned Franklin, ILMISO Apr 2024target 2028
Solar project J2703, Scott County
Solar
398 MWWithdrawn / abandoned Scott, ILMISO Sep 2022target 2027
Solar project J4004, Peoria County
Solar
392 MWWithdrawn / abandoned Peoria, ILMISO May 2025target 2032
Page 1 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)